原标题: Crews Raise the First Roof Truss on the A's Las Vegas Ballpark
第一项始终是图钉的来源。总体可信度是各份资料对上方所用开始和结束时间支持程度的加权平均;资料每比最新的一份旧 180 天,权重减半。
《拉斯维加斯评论报》:“首榀钢结构屋顶桁架于周一清晨安装”以及“6 月 1 日这一里程碑数月前就已列入施工日程”。
The follow-up: the second steel truss arch was completed on 18 August; the middle truss, the stadium's highest point, is next.[1]
The first arch capped six months of planning and took 10 days to install; the tallest arch will span 700 feet and rise 290 feet; first home games expected April 2028.[1]
MLB.com: the week of the tour 'marked the latest significant milestone with the raising of the first of six trusses that will make up the roof'; the park opens in 2028.
Before the lift: $400 million spent of $2 billion, four 200-foot shoring towers up, roof work to begin in June, anticipated completion 29 February 2028.[1]