発表済み
Rail: first light rail line · 確認日 2026-10-29
確認された段階のみ強調しています。数値と日付は計画と実証済みを区別しています。
All-electric trains every 5–10 minutes through most of the day.
“every 5–10 minutes”
2027; contractor selected for pre-construction and final design.
“beginning construction in 2027”
Nearly 10 miles with 15 stations; future extensions are separate.
“15 stations along a nearly 10-mile alignment”
Construction contractor selected
“Feb. 18, 2026”
Construction start target
このピンはニュースを追い、最新の情報を表示しています。何が変わり、何がきっかけだったかをここに示します。
記事を書き直し
Austin Transit Partnership "has“has selected Austin Rail Constructors (ARC) as the construction…marking another major step toward beginning construction in 2027",2027”, announced on Feb. 18, 2026 "The ATP Board'sThe board's approval of ARC at the Feb. 18 meeting enables ATP to begin pre-construction activities and advance final design for Austin Light Rail under“under the first phase of what will be a multibillion-dollar contract" -contract” — the release gives no dollar figure, so the pin's "above $8.2 billion" is not from this wikifigure ARC is "aa joint venture between nationally and locally recognized firmsof Stacy Witbeck and Sundt Construction"Construction and "willwill help shape and build the design and construction of nearly“nearly every aspect of the system, including the transitway,…bridges, traffic signals, utilities, drainage structures and streetscape improvements" "Austin's first light rail improvements”; the FY2026-27 budget also names Kiewit Austin Partnership (KAP) among the awarded contractors The system will featurehave 15 stations along a nearly 10-mile alignment and consist ofalignment, with all-electric trains running every 5-10 minutes throughoutthrough most of the day. Austin Light Rail is designed to be fully expandable for future extensions" - the release does not describe the pin's three-way alignment out day; the budget describes Phase 1 as 15 stops, a bridge over Lady Bird Lake and a connection to East Riverside, on a branched line of 9.8 miles north, south and east of downtown or a new bridge across Lady Bird Lake, Schedule per the approved FY2026-27 budget: preconstruction in 2026-27, construction 2027-33 and gives no opening year ARC was "identified as open for service in 2033, a planning schedule “contingent on contractor input and federal funding process”; the highest-ranked firm following a rigorous, competitive procurement process that evaluated elements including firms' experience, personnel qualifications, technical approach and design innovation", CEO says construction will begin in 2027 ARC was the highest-ranked firm after a competitive procurement that ATP completed in approximately one year, with team experience at "McKallaMcKalla Station, Austin-Bergstrom International Airport and national rail projects in Arizona, Hawaii and Utah" and several Texas-based contractors among its subcontractors "ATP completedUtah The design-build model brings the procurement in approximately one year, faster than many comparable mega projects nationwide", after a Request for Information process and "Connect & Build" industry networking events for smallconstruction partner on board sooner, aiming to prevent costly change orders and delays, and ARC will competitively bid portions of the work as design advances Funding and local businesses "The design-build model ATP has chosen to employ brings the final construction partner on board sooner in the project with the goal of earlier alignment, preventing costly change orders and future construction delays", and ARC will competitively bid portions of the work as design advances ATP CEO Greg Canally: "This is status in the approved FY2026-27 budget: NEPA review is complete with an FTA Record of Decision; ATP plans $471.8M of Light Rail Capital Fund spending in FY27 ($254.5M professional services, $160M right-of-way, $53.3M administrative, $4M betterments), with $858M of board-approved light rail appropriations in total; FY27 aims to complete Capital Investment Grants Project Development before a big, important milestone for Austin Light Rail... with Full Funding Grant Agreement ATP CEO Greg Canally: “with this contract now in place, we are on track to begin construction in 2027",2027”, while Mayor Kirk Watson called the selection "a“a major step forward in delivering the voter-mandated transit system"system”
編集@BuildDesk による
読者の写真で、出典付きのピンのメディアとは別に表示されます。食べたものや見たものを評価でき、レストランのピンでは写真上に料理をタグ付けできます。
最初の項目は常にピンの出典です。全体の確度は、各資料が上記の開始・終了時刻をどれだけ強く裏付けているかの加重平均です。最新の資料より180日古くなるごとに、重みは半分になります。
ATP(オースティン・トランジット・パートナーシップ)の最高経営責任者グレッグ・カナリー(Greg Canally)は、同機関自身の発表の中で「2027年の着工に向けて計画通り進んでいる」と述べており、日付のない年のみが示されている。完工:オースティン・トランジット・パートナーシップの2026-27会計年度承認予算(2026年9月)のプロジェクト時系列表:「2027-33年……建設・試験」、続いて「2033年……供用開始」。
Year-of-expenditure; FTA Nov 2025 profile lists $8,233.6M including finance charges.[1]
ATP's own approved budget (uploaded Sep 2026, board adoption scheduled 16 Sep 2026) shows the light rail's phase timeline with construction and testing 2027-33 and the line open for service in 2033, a year-only target.[1]
足りない点や誤りがありますか? このピンを裏付けるリンク、別の開始日・終了日とその理由、欠けている情報や誤っている情報を、自由に書いてください。AIがこのピンの出典と照らし合わせ、より良い情報源を探し、裏付けとなるページがあれば参考資料として追加します。ピン自身の出典が引き続き最も重視されます。AIは画像も確認します。別のものが写っている画像や写りの悪い画像は、後ろに回すか差し替えます。
元のタイトル: Austin Light Rail Breaks Ground on Its First Line