試運転中
Transport: airport automated people mover · 確認日 2026-10-29
確認された段階のみ強調しています。数値と日付は計画と実証済みを区別しています。
USD 3.34 billion automated people mover cost in cited report; different from 25-year contract value.
Six-station 2.25-mile elevated people mover.
Opening forecast second half 2026; systems testing does not establish public service.
Alstom Innovia APM 300 automated rolling stock.
“Alstom Innovia APM 300”
Public opening forecast
According to LAWA, the trains cannot carry passengers until LINXS fixes outstanding issues like structural repairs at the West Central Terminal Area
LAWA confirms contractor LINXS has resumed final reliability testing, debunking claims on social media.
It just seems like there's another delay, another delay, and then they got excited about it, and then there's another delay,
So it’s probably never going to happen,
このピンはニュースを追い、最新の情報を表示しています。何が変わり、何がきっかけだったかをここに示します。
読者の写真で、出典付きのピンのメディアとは別に表示されます。食べたものや見たものを評価でき、レストランのピンでは写真上に料理をタグ付けできます。
最初の項目は常にピンの出典です。全体の確度は、各資料が上記の開始・終了時刻をどれだけ強く裏付けているかの加重平均です。最新の資料より180日古くなるごとに、重みは半分になります。
記事には「システムの実証試験は2026年4月21日に開始され、30日間連続してエラーなしで動作することを実証することを目的としている」と記載されている。
Exact LAX SkyLink project reactions: ENR reports LAWA’s[3] warning about unresolved passenger-service safety issues; Mirror reports the agency’s response to rumors. Two verified dated sources; official October PDF blocked403 and not quoted. No opening date inferred from contractor targets.
Construction research 2026-10-24: LAX SkyLink is In Progress at systems testing, not passenger opening. The approximately US$3.34 billion current project estimate is separate from the original US$4.9 billion contract including decades of finance, operations and maintenance. October 2026 reporting still describes required final testing ahead; no target or almost-complete percentage proves operation. The historical April 21 systems-demonstration milestone is retained, without claiming 30 successful consecutive days. Source quote: “$4.9B 30-year” Original DBFOM contract includes operating and maintaining the system, unlike the project build estimate.[1]
Construction research 2026-10-24: LAX SkyLink is In Progress at systems testing, not passenger opening. The approximately US$3.34 billion current project estimate is separate from the original US$4.9 billion contract including decades of finance, operations and maintenance. October 2026 reporting still describes required final testing ahead; no target or almost-complete percentage proves operation. The historical April 21 systems-demonstration milestone is retained, without claiming 30 successful consecutive days. Source quote: “$3.34 billion”[1]
Exact LAX SkyLink project reactions: ENR[2] reports LAWA’s[3] warning about unresolved passenger-service safety issues; Mirror reports the agency’s response to rumors. Two verified dated sources; official October PDF blocked403 and not quoted. No opening date inferred from contractor targets.
足りない点や誤りがありますか? このピンを裏付けるリンク、別の開始日・終了日とその理由、欠けている情報や誤っている情報を、自由に書いてください。AIがこのピンの出典と照らし合わせ、より良い情報源を探し、裏付けとなるページがあれば参考資料として追加します。ピン自身の出典が引き続き最も重視されます。AIは画像も確認します。別のものが写っている画像や写りの悪い画像は、後ろに回すか差し替えます。
元のタイトル: LAX's SkyLink People Mover Starts Systems Testing
LAX SkyLink は乗客の開放ではなく、システムのテストが進行中です。 現在の約 33 億 4,000 万米ドルのプロジェクト見積もりは、数十年にわたる財務、運用、保守を含む当初の 49 億米ドルの契約とは別のものです。 2026 年 10 月の報告書には、今後必要な最終テストが記載されています。 目標がないか、ほぼ完全なパーセンテージが機能していることを証明します。 歴史的な 4 月 21 日のシステム デモンストレーション マイルストーンは維持されますが、連続 30 日間の成功は主張されません。