- Start
- May 1, 203692% CONFIDENCEfrom gov.uk · possible Jun 1, 2033 – May 1, 2036
- End
- Oct 31, 203992% CONFIDENCEfrom gov.uk
HS2 London to Birmingham Opens
- HS2 is a high-speed railway under construction in England since 2020; Phase 1 runs from London to Handsacre with a branch to Birmingham, stations at Old Oak Common, Birmingham Interchange and Curzon Street[1]
- As of May 2026, Old Oak Common-Curzon Street services are expected between May 2036 and October 2039, and Euston services between May 2040 and December 2043[1][2]
- Cost range is £87.7 billion to £102.7 billion; the government confirmed in May 2026 that it will complete the current scope from Euston to the West Midlands[1][2]
- Phase 2 was abandoned in October 2023 (Network North, £36 billion redirected) and Euston cut to six platforms; in November 2023 initial services were still forecast for 2029-2033[1][3]
- Following a June 2025 reset, operating speed is to be reduced to 320 km/h, with possible savings of £1-2.5 billion; Euston is to be part privately financed via a new Euston Delivery Company[1][2]
- Original 2010 expectation was Phase 1 opening by December 2026[1]
References 466% CONFIDENCE
The first entry is always the pin's source. Overall confidence is a weighted average of how firmly each reference supports the start and end times used above; a reference counts half as much for every 180 days older than the newest.
- [1]50%en.wikipedia.org/wiki/High_Speed_2en.wikipedia.org· Posted Sep 11, 2026· Starts Jun 1, 2033· 62% of score
Given as a target, not a fixed date, per the pin description: "…after cancellations and cost overruns. Estimated date.…"
- [2]92%High Speed 2 (HS2) Phase 1: decision to continue delivery following programme reset – Accounting Officer Assessment summary (May 2026)gov.uk· Published May 1, 2026· Starts May 1, 2036 ✓· Ends Oct 31, 2039 ✓· 37% of score
Official UK Department for Transport publication (May 2026 programme reset) gives the assured schedule range for Old Oak Common to Curzon Street as May 2036 to October 2039, superseding the pin's 2033 estimate; Transport Secretary Heidi Alexander has said there is 'no route' to a 2033 opening.[1]
- [3]74%HS2 6-monthly report to Parliament: November 2023gov.uk· Published Nov 1, 2023· 1% of score
The UK government's own 6-monthly report to Parliament states the "forecast date for initial HS2 services between Birmingham Curzon Street and Old Oak Common remains within the range of 2029 to 2033," an official but notably earlier range than the pin's stored 2036-2039 estimate, published November 2023.[1]
- [4]60%HS2: The £100BN Railway Dividing a Nation – The B1Myoutube.com· Published Aug 10, 2022· 0% of score
Suggest a correction
Something missing or wrong? Say it in your own words: a link that backs this pin up, a different start or end date and why, or a fact it lacks or gets wrong. The AI checks it against this pin's sources, searches for better ones, and adds any page that backs you up. The pin's own sources still count most.