Mumbai-Ahmedabad Bullet Train Opens
- The Mumbai-Ahmedabad high-speed rail line is India's first bullet-train corridor: 508 km, 12 stations, built and operated by NHSRCL with Japanese Shinkansen technology (E10 Series / B28 "Vande Bullet") and technology transfer under Make in India[1]
- Specs: standard gauge, 25 kV AC, ETCS Level 2, operating speed 320 km/h (design 350 km/h), a 353 km viaduct; trains are expected to cover the route in two hours versus 5 h 40 min for the current Vande Bharat[1]
- Construction began February 2021 after COVID delays; the planned opening is 15 August 2027 for the Surat-Bilimora section (then Vapi-Surat) and 2029 for the full line, so the pin's 2028 date is earlier than the sources' opening dates[1][2][3]
- Railways Minister Ashwini Vaishnaw said on 1-2 January 2026 that the first bullet train would start on Independence Day, 15 August 2027[2][3]
- Cost is about Rs 1.1 lakh crore, 81% funded by a JICA loan; Rs 67,486 crore had been spent and 47% of civil works completed by October 2024[1]
References 362% CONFIDENCE
The first entry is always the pin's source. Overall confidence is a weighted average of how firmly each reference supports the start and end times used above; a reference counts half as much for every 180 days older than the newest.
- [1]50%en.wikipedia.org/wiki/Mumbai%E2%80%93Ahmedabad_high-speed_rail_corridoren.wikipedia.org· Posted Sep 11, 2026· Starts Aug 15, 2028 ✓· 57% of score
Given as a target, not a fixed date, per the pin description: "…i to Ahmedabad trip to about two hours. Estimated date.…"
- [2]80%First bullet train to run between Mumbai Ahmedabad on 15 August 2027, says Ashwini Vaishnawnewsonair.gov.in· Published Jan 1, 2026· 21% of score
India's official government news service reports Railways Minister Ashwini Vaishnaw's statement that the first section (Surat-Bilimora) starts service on 15 August 2027, with the full Mumbai-Ahmedabad corridor phased in through 2029; left without an exact day since sources disagree on which milestone counts as the full corridor 'opening'.[1]
- [3]78%India's first bullet train to commence operations on August 15, 2027deccanherald.com· Published Jan 1, 2026· 21% of score
Deccan Herald, a major Indian daily, independently corroborates the government's phased timeline: first section in 2027, full Mumbai-Ahmedabad corridor by 2029.
Suggest a correction
Something missing or wrong? Say it in your own words: a link that backs this pin up, a different start or end date and why, or a fact it lacks or gets wrong. The AI checks it against this pin's sources, searches for better ones, and adds any page that backs you up. The pin's own sources still count most.