VDOT 및 출처에 따라 예정대로 제공: "수정된 프로젝트 일정은... 최종 완료 날짜를 2027년 8월 27일로 설정합니다."
Construction research 2026-10-24: The full HRBT expansion includes the new tunnels, trestles and widened highway. Boring and partial road openings do not complete that scope. VDOT’s newsroom continues to describe the US$3.9 billion expansion, with road and tunnel finishing works continuing into 2027. Source quote: “including the $3.9 billion Hampton Roads Bridge-Tunnel Expansion”[1]
VDOT's own newsroom confirms the HRBT Expansion's substantial completion was moved to February 2027 with final completion in August 2027, matching the pin's stored August 27, 2027 date. Construction research 2026-10-24: The full HRBT expansion includes the new tunnels, trestles and widened highway. Boring and partial road openings do not complete that scope. VDOT’s newsroom continues to describe the US$3.9 billion expansion, with road and tunnel finishing works continuing into 2027. Source quote: “another major part of the $3.9 billion project is taking down much of the decades-old infrastructure”[1]
WTKR reports the project's substantial completion date is now "February 26, 2027, with final completion set for August 27, 2027" - matching the pin's stored date exactly.
빠지거나 잘못된 점이 있나요? 이 핀을 뒷받침하는 링크, 다른 시작일이나 종료일과 그 이유, 빠지거나 잘못된 사실을 자신의 말로 알려주세요. AI가 이 핀의 출처와 대조하고 더 나은 자료를 찾아, 뒷받침하는 페이지를 추가합니다. 핀 자체의 출처가 여전히 가장 중요하게 반영됩니다. AI는 이미지도 확인합니다. 다른 것을 보여주거나 제대로 보여주지 못하는 이미지는 뒤로 옮기거나 교체합니다.
The Hampton Roads Bridge-Tunnel on I-64 is one of the region's most congested corridors.
How: Expand the roughly 10-mile I-64 stretch across the mouth of the James River with new harbor-crossing tunnels, to ease congestion.
원본 제목: Hampton Roads Bridge-Tunnel Expansion
전체 HRBT 확장에는 새로운 터널, 가대 및 확장된 고속도로가 포함됩니다. 지루하고 부분적인 도로 개방은 해당 범위를 완성하지 않습니다. VDOT의 뉴스룸은 도로 및 터널 마무리 작업이 2027년까지 계속되는 39억 달러 규모의 확장에 대해 계속해서 설명하고 있습니다.