The first entry is always the pin's source. Overall confidence is a weighted average of how firmly each reference supports the start and end times used above; a reference counts half as much for every 180 days older than the newest.
1,500 MW Luzerne County hyperscale campus scheduled for late 2028 initial commissioning.
Something missing or wrong? Say it in your own words: a link that backs this pin up, a different start or end date and why, or a fact it lacks or gets wrong. The AI checks it against this pin's sources, searches for better ones, and adds any page that backs you up. The pin's own sources still count most. A picture that shows something else, or shows it badly, is looked at too, and moved down or replaced.
Just over 2.5 million square feet; single-story buildings
“2.5 million”
998.8 acres across two townships; approximate mapped outline is not the cadastral acreage
“998.8 acres”
2.2 GW requested/planned grid service; not committed IT load or operating capacity
“2.2 gigawatts”
Six single-story data centers: four in Covington Township and two in Clifton Township
“six”
Revised six-building application reported
“six”
Township acknowledges receipt of conditional-use application
“Conditional Use Application Received”
Hearing dates tabled while township seeks hearing officer
“Since there is no hearing officer at this time”