The first entry is always the pin's source. Overall confidence is a weighted average of how firmly each reference supports the start and end times used above; a reference counts half as much for every 180 days older than the newest.
Start is the first dated public record (county tax-break discussion, 18 Feb 2025); the pin's existing May 2025 start also falls in the review period. NorthPoint publishes only a six-year development period and no completion date, so no end date is set.
Cited in the project timeline.[1]
Cited in the project timeline.[1]
Cited in the project timeline.[1]
Cited in the project timeline.[1]
Something missing or wrong? Say it in your own words: a link that backs this pin up, a different start or end date and why, or a fact it lacks or gets wrong. The AI checks it against this pin's sources, searches for better ones, and adds any page that backs you up. The pin's own sources still count most. A picture that shows something else, or shows it badly, is looked at too, and moved down or replaced.
About 1,300 acres (1,280 in other coverage)
“The total property is 1,300 acres. The campus will be built on 616 acres and the remaining 684 acres will stay undeveloped”
Six years (no dated start or completion published)
“More than 1,300 construction jobs over the six-year development period”
Denied locally; developer appeal pending in Commonwealth Court
“NorthPoint has so far been unable to secure final approval for the project.”
15 data center buildings, 4 ancillary buildings, switchyard and substation
“The 15-building data center project is proposed on a 1,280-acre site near Interstate 81.”
County LERTA tax break for 15-building campus discussed by county council committee
“NorthPoint Development is seeking a Luzerne County real estate tax break for a 15-building data center on a 1,280-acre site in Hazle Township.”
Project before the Hazle Township planning commission
“The project been in front of the planning commission since April.”
Supervisors table the vote before a packed hall
“The board heard the people's concerns and decided to table the vote for a later date.”
Supervisors unanimously reject the land development application
“the Hazle Township Board of Supervisors unanimously rejected a land application that would have enabled construction of the Project Hazelnut data center campus proposed by NorthPoint Development.”
DEP public hearing on Chapter 105 and Chapter 102 permits
“DEP held the meeting and public hearing on two of NorthPoint's pending permits with the agency, which are:”
County judge rebukes NorthPoint's appeal of the denial
“The move comes less than two weeks after a judge rebuked an effort by data center developer Northpoint to appeal the Township's denial last fall of Project Hazelnut.”
Township pauses new data center applications for six months
“the Hazle Township Board of Supervisors unanimously passed a municipal curative amendment that pauses consideration of any new data center applications for six months to allow the township to update its zoning ordinances for this industrial use.”
NorthPoint appeals to Commonwealth Court
“Hazle Township supervisors rejected the proposal, and a Luzerne County judge later upheld objections to the development. The company has since appealed the matter to Commonwealth Court.”
NorthPoint announces $165 million community benefits package
“The developer of the planned Project Hazelnut data center complex in Hazle Township announced a $165 million community benefits package”
NorthPoint Development proposes Project Hazelnut, a 15-building data center campus on a former strip mine of about 1,280 acres near the Humboldt Industrial Park in Hazle Township. Township supervisors unanimously rejected the land development application on 14 November 2025, a county judge rebuked NorthPoint's appeal, and the developer has appealed to Commonwealth Court while pursuing state DEP permits. Hazle Township paused new data center applications for six months on 8 June 2026. NorthPoint promises a $165 million community benefits package, more than 900 permanent jobs and wastewater-only cooling if the project is approved.