Only the month is supported. 2012-11-01 is a timeline anchor, not a confirmed operating day. Both refurbished units reach commercial service by November 2012. This pin covers the combined programme; day 1 is a month-level anchor.
Operator retrospective confirms successful 2012 completion of Bruce A restart and return of Units 1 and 2. 2022 unit output: 6.7 and 5.9 TWh.[1]
Something missing or wrong? Say it in your own words: a link that backs this pin up, a different start or end date and why, or a fact it lacks or gets wrong. The AI checks it against this pin's sources, searches for better ones, and adds any page that backs you up. The pin's own sources still count most. A picture that shows something else, or shows it badly, is looked at too, and moved down or replaced.
Both refurbished units reach commercial service by November 2012. This pin covers the combined programme; day 1 is a month-level anchor.[1]
1506 MW electrical capacity. Historical generating capacity; not a claim about current output.[2]
Project cost: CAD 4,800,000,000. Combined Units 1 and 2 refurbishment/restart programme; not a per-unit amount or later Units 3–8 programme. Source quote: “increased to C$4.8 billion”. Stated currency; no foreign-exchange or inflation conversion.[1]
Only the month is supported. 2012-11-01 is a timeline anchor, not a confirmed operating day. Both refurbished units reach commercial service by November 2012. This pin covers the combined programme; day 1 is a month-level anchor.
Photo: Bruce Power. Bruce A Unit 3, from the operator’s 2022 annual report. This provides Bruce A station context and does not depict Unit 1 or Unit 2 restart work. Source and credit.
Power generation1.46 GW · Historical original design net ratings: Units 1 and 2 each 732 MWe, combined 1,464 MWe. Not current uprated output or incremental restart capacity. Both returned in 2012. Unit 2 corroboration: https://world-nuclear.org/nuclear-reactor-database/details/BRUCE-2 · source