A target year, per Aramco's[2][3][4] Q2 2026 results release (3 August 2026): phase two 'continued with procurement and construction activities, with an expected completion in 2027' - a bare year, so its last day.
Aramco's[1][3][4] Q2 2026 results (3 August 2026): 'phase two continued with procurement and construction activities, with an expected completion in 2027' - the page that dates this pin.
Aramco[1][2][4], 26 February 2026: Jafurah production started in December 2025 and the field is to reach 2 bscfd of sales gas by 2030.
Aramco[1][2][3], 14 August 2025: the Jafurah Field Gas Plant and Riyas NGL Fractionation Facility go into the JMGC leaseback, and 'development of subsequent phases is well on track'.
Saudi Press Agency's report of the 30 June 2024 Jafurah II and Master Gas System III signing ceremony, with its photographs of the contract signings.[1]
Something missing or wrong? Say it in your own words: a link that backs this pin up, a different start or end date and why, or a fact it lacks or gets wrong. The AI checks it against this pin's sources, searches for better ones, and adds any page that backs you up. The pin's own sources still count most.