Delayed, per iusm.co.kr: S-Oil told its 3 August 2026 call it is "2027년 초 상업가동을 목표로" (targeting commercial operation in early 2027) after pre-commissioning and start-up; KBS (Feb 2026) gives the target as January 2027, so the month's last day.
S-Oil's Q1 2026 call: mechanical completion end of June, commissioning in the second half, commercial operation early next year.[1]
Hankyung (via Nate): 95% progress, June mechanical completion, TC2C yields over 70%, 150 MW LNG power plant, and the Hormuz closure's effect on crude supply.
KBS News report: 94% complete, all equipment installed by end of June, commissioning in the second half and commercial operation targeted for January 2027.[1]
Site visit: 85% complete on 15 Oct 2025, commercial operations scheduled for the second half of 2026 (the original date), 9.26 trillion won, TC2C and cracker specs, Aramco as largest shareholder.[1]
Something missing or wrong? Say it in your own words: a link that backs this pin up, a different start or end date and why, or a fact it lacks or gets wrong. The AI checks it against this pin's sources, searches for better ones, and adds any page that backs you up. The pin's own sources still count most.