- Revolution Wind completed installation of its 65th and final Siemens Gamesa turbine, reported on 18 September 2026; Ørsted said commissioning continues with a target of full operations by the end of the year[1]
- The first turbine went up in September 2024 and the farm began delivering power to the New England grid in mid-March 2026 at about 90% complete; by mid-August it was more than 95% complete with 61 of 65 turbines installed[1][3][4][5]
- Revolution Wind is 704 MW, 400 MW for Rhode Island and 304 MW for Connecticut under 20-year power purchase agreements, enough for about 350,000 homes, and is owned 50/50 by Ørsted and Skyborn Renewables; media reports put the investment at $6.2 billion[1][3]
- Two federal stop-work orders in 2025 (August and December) were both overturned in court, and a preliminary injunction issued in January 2026 still keeps the second order from being enforced[1][3]
- Ørsted first planned commercial operation for 2025 but moved it to 2026 because contamination at the former naval disposal site where the onshore substation is built took longer to clear than expected[2]
- Connecticut's energy department estimates the farm will save New England ratepayers $500 million a year in wholesale energy costs once at full commercial operation[5]
References 570% CONFIDENCEOverall confidence: 70%How well the pin's source and references back up its dates.Weighted average of how firmly 5 references, the source included, support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins from 50% to 74% confidence
The first entry is always the pin's source. Overall confidence is a weighted average of how firmly each reference supports the start and end times used above; a reference counts half as much for every 180 days older than the newest.
- [1]40%maritime-executive.com/article/us-offshore-wind-project-revolution-wind-installs-last-turbinemaritime-executive.com· Posted Oct 3, 2026· Starts Dec 31, 2026 ✓· 24% of score
Stated: Ørsted CEO Rasmus Errboe, 13 Aug 2026 (CT Mirror[4]): the four remaining turbines allow "the project to reach full commercial operation by the end of 2026"; Ørsted confirmed on 18 Sep 2026 that the last turbine is in and commissioning continues "with a target by the end of the year for full operations" (Maritime Executive).
- [2]75%Waiting in the wind: Revolution Wind delayed to 2026 - Renewable Energy Worldrenewableenergyworld.com· Added Oct 3, 2026· 24% of score
Why operation slipped from 2025 to 2026.[1]
- [3]80%Revolution Wind offshore project more than 95% complete - Offshore Magazineoffshore-mag.com· Published Aug 20, 2026· 20% of score
Progress, court history and the end-of-year target.[1]
- [4]85%Revolution Wind project on track for completion this year, developer says - CT Mirrorctmirror.org· Published Aug 13, 2026· 20% of score
Errboe's full-commercial-operation-by-end-2026 statement.[1]
- [5]80%Revolution Wind Starts Delivering Power - offshoreWIND.bizoffshorewind.biz· Published Mar 14, 2026· 11% of score
First power and the savings estimate.[1]
Suggest a correction
Something missing or wrong? Say it in your own words: a link that backs this pin up, a different start or end date and why, or a fact it lacks or gets wrong. The AI checks it against this pin's sources, searches for better ones, and adds any page that backs you up. The pin's own sources still count most. A picture that shows something else, or shows it badly, is looked at too, and moved down or replaced.