The first entry is always the pin's source. Overall confidence is a weighted average of how firmly each reference supports the start and end times used above; a reference counts half as much for every 180 days older than the newest.
Opening / first-lease date: projected opening recorded only to the month (March 2028) in The Bourne Apartments - Resident Meeting, April 6, 2026 (Pennrose[4] / Contour Housing Partners); the pin sits on the last day of that month. Not yet open: this is the projected opening, not a confirmed date. Confidence: medium. Existing occupied 205-unit property (Bourne tower 150 Smith St, reported built 1954; Kenney garden apts reported built 1965 - listing sites, low weight; prior LIHTC rehab late 1990s/PIS 2000 per Pennrose deck and LIHTC database). The only forward date is Pennrose/Contour's April 6, 2026 resident-meeting schedule: acquisition closing and construction start August 2026 (PILOT approved by Newburgh council 13 Apr 2026, 7-0), tenant-occupied rehab complete March 2028. This is rehab completion, not a first opening; if the pin needs an original opening date, 1954 (Bourne) is the only sourced figure but low confidence.
Local paper reporting the 7-0 PILOT vote and inspection-linked conditions[1]
Mid-Hudson News report on the 33-year PILOT
Operator deck with rehab scope, milestones and March 2028 completion target[1]
News 12 report on the up-to-$3M tax relief request and tenant conditions
Something missing or wrong? Say it in your own words: a link that backs this pin up, a different start or end date and why, or a fact it lacks or gets wrong. The AI checks it against this pin's sources, searches for better ones, and adds any page that backs you up. The pin's own sources still count most. A picture that shows something else, or shows it badly, is looked at too, and moved down or replaced.
“Submitted PILOT Proposal to City Manager: May 2025”
Purchase and sale agreement executed
“Execution of Purchase & Sale Agreement: June 30, 2025”
Financing application submitted to NYS HCR
“Financing Submission to NYS HCR: November 2025”
State and National Park Service historic-preservation approval
“SHPO & NPS Approval of Historic Preservation: January 2026”
City Council approves 33-year PILOT (7-0, one abstention)
“The resolution passed 7-0, with Councilmember Ronald Zorilla abstaining.”
HCR approval of financing (planned, not confirmed)
“HCR Approval of Financing: May 2026”
Acquisition closing and construction start (planned, not confirmed)
“Acquisition Closing & Construction Commencement: August 2026”
Estimated completion
“Construction completion is scheduled for March 2028”
Opening date: projected opening March 2028 (month precision; no exact day published). Source: The Bourne Apartments - Resident Meeting, April 6, 2026 (Pennrose / Contour Housing Partners). Operator listing and program documents were last reviewed October 10, 2026.
Planned / coming-soon project. The current page provides project information or an interest form; an open application window and move-in date were not verified.
Dollar rents were not verified in the project-specific sources checked. Income limits do not establish a fixed monthly rent. Consult the linked property leasing information.