The first entry is always the pin's source. Overall confidence is a weighted average of how firmly each reference supports the start and end times used above; a reference counts half as much for every 180 days older than the newest.
Opening / first-lease date: first lease-up recorded as July 1, 2025 (Governor Hochul announces Perry Homes I in Buffalo welcomes first residents). Date is the governor's announcement (July 1, 2025), so first move-ins occurred on or shortly before. Phase I of redevelopment of Commodore Perry Homes (originally built 1930s).
BMHA release: applications open, lottery Aug 15, 2025, move-ins into 2026 when all Phase I units are completed.[1]
State release with 405 units, $254 million financing, amenities and first residents.[1]
Groundbreaking coverage with Commodore Perry Tenants Council president quoted; first units expected August 2025.[1]
Start of construction announcement; $254 million, 405 apartments, 27 buildings.[1]
405 affordable apartments in 27 buildings
“When complete, Phase I will consist of 405 affordable apartments in 27 newly constructed buildings”
Demolition April 2024; first residents July 2025; all units completed into 2026
“a cycle of move-ins will continue throughout 2025 and into 2026, when all the units in Phase I are completed.”
Phase I leasing and move-ins under way since July 2025; remaining Phase I units due into 2026; Phase II planned
“The first residents will move into their new homes this summer, and a cycle of move-ins will continue throughout 2025 and into 2026, when all the units in Phase I are completed.”
Groundbreaking: start of construction announced
“Governor Kathy Hochul today announced the start of construction on the redevelopment of the Commodore Perry Homes”
First residents move into Phase I
“Governor Kathy Hochul today announced that Phase I of Perry Homes in Buffalo’s First Ward has welcomed its first residents.”
Lottery for the 121 non-subsidized units
“A live streamed lottery will take place on August 15, 2025.”
All Phase I units completed (move-ins continue into 2026); completion not yet confirmed
“a cycle of move-ins will continue throughout 2025 and into 2026, when all the units in Phase I are completed.”
Something missing or wrong? Say it in your own words: a link that backs this pin up, a different start or end date and why, or a fact it lacks or gets wrong. The AI checks it against this pin's sources, searches for better ones, and adds any page that backs you up. The pin's own sources still count most. A picture that shows something else, or shows it badly, is looked at too, and moved down or replaced.
Opening date: first lease-up July 1, 2025. Source: Governor Hochul announces Perry Homes I in Buffalo welcomes first residents. Operator listing and program documents were last reviewed October 10, 2026.
Direct all leasing inquiries to Buffalo Municipal Housing Authority: perryhomes@bmhahousing.com, 716-855-6711 ext. 100 or 101. Leasing does not establish completion of every planned phase. Leasing phone: 716.855.6711.
Dollar rents were not verified in the project-specific sources checked. Income limits do not establish a fixed monthly rent. Consult the linked property leasing information.