ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins65% CONFIDENCEOverall confidence: 65%How well the pin's source and references back up its dates.Weighted average of how firmly 3 references, the source included, support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins from 50% to 74% confidence
Start is the first Epoch[1] AI satellite observation (land clearing, 24 July 2024); end is Epoch's estimate for Building 3 (1 January 2028).Meta's Los Lunas campus in New Mexico reached an estimated 118 MW of IT power and about 134,000 H100-equivalents with Building 2 operational (Epoch AI estimate, 26 October 2026). Epoch projects a third building and 218 MW by 2028.
1.00