ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins66% CONFIDENCEOverall confidence: 66%How well the pin's source and references back up its dates.Weighted average of how firmly 4 references, the source included, support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins from 50% to 74% confidence
EIA-860M lists the 180 MW plant (69151) with a proposed date of 1 Sep 2026 and status "Testing"; the ERCOT queue entry 24INR0306 (183.76 MW) shows a proposed COD of April 2026. NADBank[1] only says "under construction".Goshe Energy Storage (Cleanview lists Excelsior Energy Capital) is building a portfolio of seven battery systems totalling 180 MWac in Cameron County, Texas for ERCOT, with up to 85M USD of NADBank loan reserved; the total project cost is not published.
1.00