ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins54% CONFIDENCEOverall confidence: 54%How well the pin's source and references back up its dates.Weighted average of how firmly 2 references, the source included, support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins from 50% to 74% confidencein 72 days
Aligned's 24 July 2025 release targeted initial capacity in mid 2026; Cleanview now dates the first two buildings (under construction) to 2027, the later two to 2028; no Aligned update was found.[1]Aligned Data Centers is building a four-building, about 346 MW data center campus on 197 acres beside the retired AEP Conesville power plant in Coshocton County, Ohio; Cleanview estimates 2.7B USD, Aligned says only "multi-billion".
$2.7B