Microsoft's[4][5] press release dated June 23, 2026 says the company "on Tuesday announced that it has completed construction of its first datacenter facility in the Village of Mount Pleasant, after bringing equipment online and conducting startup activities in April. The facility is now fully operational."
Racine County Eye covers the opening with Microsoft's[1][4][5] own answers on the GB200 cluster, jobs, the old Foxconn site, WEC Energy Group's projected demand and new PSC data-center tariffs, and notes the supercomputer claim is self-reported.
Wisconsin Public Radio reports the 315-acre facility fully operational after equipment came online in April, about 550 staff, the second building due in 2028 and village approval for up to 15 more datacenters.[1]
Brad Smith's post sets out the $3.3 billion pledge for the first Mount Pleasant datacenter, a further $4 billion for a second, closed-loop liquid cooling, pre-paid energy infrastructure and the We Energies partnership.[1]
Scott Guthrie's post describes Fairwater's 315-acre site, three buildings with 1.2 million square feet under roof, and its NVIDIA GB200 racks of 72 Blackwell GPUs working as one supercomputer.[1]