State Water Board Votes on Sites Reservoir's Final Water Right Permit
- Governor Newsom announced on 24 September, during Climate Week in New York, that Sites Reservoir is moving closer to construction: late the previous week the Sites Project Authority advanced the project into an investment period, signalling that the State Water Board's revised water right permit can support a viable reservoir[1]
- The final permit goes before the State Water Resources Control Board on 4 November 2026, with written comments due 5 October[4][6]
- The revised draft, released 3 September, keeps the annual diversion cap at 986,000 acre-feet but drops the March draft's test that barred diversions whenever Delta outflow fell below 55 percent of unimpaired flow, and gives the project a path to show water is available from local creeks; it follows 32 hearing days with 21 parties and 60 witnesses[5]
- The off-stream reservoir west of Maxwell would hold up to 1.5 million acre-feet from the Sacramento River, enough for over 4.5 million homes for a year, and would supply up to 200,000 acre-feet in emergency-declared droughts, send water to wildlife refuges and draw about 187,000 recreational visitors a year[1]
- The state added nearly $269 million earlier this year, making the project eligible for $1.363 billion from the Water Storage Investment Program (Propositions 1 and 4); the California Water Commission puts total cost at $6.2 billion to $6.8 billion[1][2]
- The Authority has begun choosing a construction manager at risk for the reservoir and roads portion; the Water Commission's schedule expects water-right and other permits in 2026, with construction and commissioning running into the 2030s[2]
- Newsom earlier streamlined CEQA judicial review, and the project defeated a legal challenge to its environmental review[1]
参考资料 6可信度 81%总体可信度: 81%该图钉的来源和参考资料对其日期的支持程度。包括来源在内的 6 份资料对图钉开始和结束时间支持程度的加权平均;资料每比最新的一份旧 180 天,权重减半显示所有可信度不低于 75% 的图钉
第一项始终是图钉的来源。总体可信度是各份资料对上方所用开始和结束时间支持程度的加权平均;资料每比最新的一份旧 180 天,权重减半。
- [1]75%gov.ca.gov/2026/09/24/californias-largest-new-water-storage-project-takes-a-major-step-forwardgov.ca.gov· 发布于 2026年9月30日· 开始 2026年11月4日 ✓· 占评分 17%
Governor's office, 24 Sep 2026: "the final permit will go before the State Water Board on November 4"; the State Water Board's 3 Sep release names the same 4 November public meeting. The meeting's clock time is not given, so the pin is all day.
- [2]80%Sites Reservoir advances toward construction after revised water right - WaterWorldwaterworld.com· 发表于 2026年9月28日· 占评分 17%
Adds the $6.2-6.8 billion cost estimate, the Water Commission schedule and the construction-manager-at-risk selection.[1]
- [3]72%Sites Reservoir moves closer to construction - California Construction Newscaliforniaconstructionnews.com· 发表于 2026年9月28日· 占评分 17%
Trade-press coverage confirming the investment period and the 4 November Board date.[1]
- [4]80%Newsom announces Sites Reservoir moves closer to construction ahead of key permit vote - KRCRkrcrtv.com· 发表于 2026年9月24日· 占评分 17%
Independent local report of the 24 Sep announcement: "The final water-right permit is set to go before the state water board on Nov. 4, 2026."[1]
- [5]85%California revises draft water right decision for Sites Reservoir - Smart Water Magazinesmartwatermagazine.com· 发表于 2026年9月8日· 占评分 16%
Explains what the revision changed: the 986,000 acre-foot cap is unchanged, the Delta-outflow test is dropped, and the hearing record behind it.[1]