Start: AZFamily[5] gives April 2021 for the start of construction (a November 2022 Taiwan News[6] piece says work started 18 months earlier, roughly May 2021). End: TSMC says high-volume production began in 4Q24. Both are month or quarter precision, not exact days.
Fab 1 is the first wafer fab on TSMC's north Phoenix campus, the plant behind the original US$12 billion Arizona announcement. Construction began in April 2021, the first production tools moved in at a December 2022 ceremony attended by President Biden, and TSMC reports high-volume N4 production in the fourth quarter of 2024 with yields comparable to its Taiwan fabs. A labor shortage had pushed its start from late 2024 to 2025 before the schedule recovered.
$12B