Phase 1 of Beijing Subway Line 28 runs Line 28 (the former CBD line) is an all-underground, 8.877 km (5.516 mi) with 9 stations km, nine-station light metro under Chaoyang district, from Dongdaqiao to Guangqudonglu beneath Chaoyang district, with a planned opening in 2029 - the year this pin marks The Guangqudonglu, using six-car linear-motor trains at up to 80 km/h; Beijing's planning authority approved its feasibility report in September 2020 Schedule slipped repeatedly: the line was formerly known as the CBD linefirst planned to start in 2019 and carries open in 2022, then moved to a 2021 start and 2025 opening; in August 2023 Chaoyang district officials said a normal metro build takes about six years and gave around 2029, seven years later than the planned name M28;original plan Why it is underground, with an operating speed of 80 km/h Rolling stock is 6-car Type L linear motor stock, similar to that was slow: complex traffic around the CBD required road diversions, utility relocation and tree removal before digging; Dongdaqiao station's diaphragm walls began on the Capital Airport Express 25 October 2023, Jingguangqiao's first-phase traffic diversion finished on 11 November, and Guangzhou Metro Lines the core-area station (contract section 4, 5 China Railway Tunnel Bureau) started steel-column work on 13 November Dongdaqiao is a four-line interchange (Lines 6, 17, 22 and 6 History: planning authorities proposed an underground automatic people mover through the CBD in August 2015; 28) with a 46.8 m-deep pit and 83 m-deep diaphragm walls, reported as Beijing's deepest metro-station pit; China Railway 16th Bureau is the August 2019 plan, builder Funding and design: tender notices in the most recent announced, redesigned itofficial public-resource system list financing as a higher-capacity light metro on the present 8.877 km, 9-station alignment;40 per cent government investment and 60 per cent other sources; a feasibility study total project cost was approved not found in October 2020; and construction started any page opened. The 2020 approval also folded in July 2021 The nine stations are Dongdaqiao (interchange with Lines 6, 17 and Pinggu), Jintai Xizhao (Line 10, Pinggu), Guanghualu, Hexinqu, Dawang Lu (Lines 1, 14), Beijing East railway station (Sub-Central, BOP), Dajiaoting (Line 7), Guangqulu and Guangqudonglu, with about 2.2 km of Line 22 (Pinggu line) from Dongdaqiao to Jingguangqiao for simultaneous construction In August 2025 the municipal infrastructure investment company published an 'integrated plan' with the line at about 8.7 km, nine stations, six of them interchanges, and a depot on about 17 hectares at Guangqudonglu The line is still listed as under constructionGuangqu Donglu, so station names and length may still be refined
독자들의 사진으로, 출처가 있는 핀의 미디어와 별도로 표시됩니다. 먹거나 본 것을 평가하고, 레스토랑 핀에서는 사진에 바로 요리를 태그해 보세요.
첫 번째 항목은 항상 핀의 출처입니다. 전체 신뢰도는 각 자료가 위의 시작·종료 시각을 얼마나 확실히 뒷받침하는지에 대한 가중 평균이며, 자료는 최신 자료보다 180일 오래될 때마다 가중치가 절반이 됩니다.
영어 위키피디아에는 달이 없는 해인 "2029년에 개장할 예정"이라고 나와 있어 해당 날짜는 그 해의 끝을 의미한다.
Beijing News on the August 2025 public consultation: about 8.7 km, nine stations, six interchanges, 17-hectare depot at Guangqu Donglu.[1]
Describes Dongdaqiao station works: 46.8 m pit, 83 m diaphragm walls, four-line interchange.[1]
Beijing News: official 2029 opening guidance, slipped schedule history (2022 -> 2025 -> 2029), station start dates, 2025/2032/2047 ridership forecasts, headways.[1]
CGTN via Visit Beijing: feasibility report approved by the municipal development and reform commission; 8.9 km, nine stations, five transfer stations.
빠지거나 잘못된 점이 있나요? 이 핀을 뒷받침하는 링크, 다른 시작일이나 종료일과 그 이유, 빠지거나 잘못된 사실을 자신의 말로 알려주세요. AI가 이 핀의 출처와 대조하고 더 나은 자료를 찾아, 뒷받침하는 페이지를 추가합니다. 핀 자체의 출처가 여전히 가장 중요하게 반영됩니다. AI는 이미지도 확인합니다. 다른 것을 보여주거나 제대로 보여주지 못하는 이미지는 뒤로 옮기거나 교체합니다.
원본 제목: Beijing Subway Line 28 Opens Under the CBD