Sources place the new dam's completion in 2025 - some reporting it already in operation by autumn 2025 - with the powerplant's full restart following in 2026; no single confirmed completion date was found.
Swissdams (in French) states KWO is replacing the dam "de 2019 à 2025" (from 2019 to 2025), corroborating a 2025 completion target close to the pin's stored 31 December 2025 date.
Implenia, a contractor on the project, gives an October 2025 completion in its facts summary but a 2026 target in its narrative text - an ambiguity the reference itself flags, consistent with the pin's lower "estimated" confidence and its own note that no single confirmed date was found.