…Hondo platform offshore California to come back online in by the end of September 2026, the third Santa Ynez Unit platform restarted after Heritage and Harmony. On its August earnings call management said the 45-year-old platform needed about 50% more work than expected and that it was "hoping" to hit the September timing. Hondo is expected to produce lower-sulfur crude that…
…in early April 2026, with Harmony also producing On the 11 August second-quarter call management put the Hondo restart “by the end of September”, but said the 45-year-old platform had needed “about 50% more work than we expected” — a “tremendous amount of structural work” and controls “completely changed out” — and that the team was “hoping we can hit that timing in September” The date has already slipped once: Sable's April corporate update put Hondo online in June 2026, before its 10 August release moved it to September An average of about 47 wells at Harmony …Q4 2026 with full implementation anticipated in 2027 Hondo is the easternmost platform, where crude runs lowest in sulfur, so blending its oil into the field's output should cut the sulfur penalties Sable pays on SYU barrels Sable reported $18.5 million of non-recurring demurrage charges in … from September 2026 to take more SYU barrels On 19 August a federal court fined Sable $1.449 million for restarting the onshore Santa Ynez Pipeline System without the State Fire Marshal's authorization, but declined to order it shut, since PHMSA had since approved the restart plan; it also refused California's bid to block the Energy Department's Defense Production Act order keeping the line running, and California appealed on 20 August From 8 September Sable crews began excavating 12 stretches of the pipeline that carries SYU oil onshore, where federally mandated tests flagged possible corrosion; any spot with wall loss of 40% or more must be repaired Chairman and CEO Jim Flores said the team…
读者上传的照片,与图钉带来源的媒体分开显示。你可以为吃到或看到的内容评分,在餐厅图钉上还能直接在照片上标记菜品。
第一项始终是图钉的来源。总体可信度是各份资料对上方所用开始和结束时间支持程度的加权平均;资料每比最新的一份旧 180 天,权重减半。
延期。根据Sable于2026年8月11日召开的第二季度财报电话会议,“Hondo平台预计将于9月底前重启”(此前4月给出的目标是6月),管理层仅表示“希望”能赶上这一时间节点;截至2026年9月28日,尚未宣布重启。
Reports Sable crews "have been out digging up pipeline since September 8" at 12 suspected corrosion sites on the line that carries oil from platforms Harmony, Heritage and Hondo.[1]
Sable's own filing: the Central District of California fined it $1.449 million for restarting the onshore Santa Ynez Pipeline System without OSFM authorization but refused to order the pipeline shut, and denied California's injunction against the DPA order.[1]
Quotes the quarterly report: Sable "expects Platform Hondo to come online in September 2026".[1]
Management on the Q2 2026 call: "Platform Hondo is expected to restart by the end of September", after "about 50% more work than we expected" on the 45-year-old platform, while "hoping we can hit that timing in September".[1]
有遗漏或错误吗?用你自己的话说明:能佐证此图钉的链接、不同的开始或结束日期及理由,或缺失、有误的信息。AI 会对照此图钉的来源进行核实,搜索更好的来源,并添加任何支持你说法的页面。图钉自身的来源仍然最重要。AI 也会查看图片:显示的是别的东西或显示效果差的图片会被移到后面或替换。
原标题: Sable Restarts Platform Hondo, the Third Santa Ynez Unit Platform