原标题: Logan Closes Runway 9-27 for 75 Days to Finish Its Overrun Safety Bed
第一项始终是图钉的来源。总体可信度是各份资料对上方所用开始和结束时间支持程度的加权平均;资料每比最新的一份旧 180 天,权重减半。
据 Massport[5],已排定:“9-27 跑道将自 8 月 31 日起关闭 75 天,仅有非常有限的可用时段”,“工程预计在感恩节前完成”——75 天至 11 月 13 日结束。
NBC Boston[4] from the site: the bridge deck for a fully loaded 747, two construction years of 75 days each, Massport's[1][5] Sarah Dennechuk on reopening after day 75.
Revere Journal carries Massport's[1][5] phase-two notice for neighbouring communities: 75 days from 31 August, pile driving in approved daytime hours.
Boston.com: phase two begins 31 August, closing Runway 27 for about 75 days, finishing before Thanksgiving; capacity and delay impacts.
Massport's[1] phase-one notice: two 75-day closures, the first from 2 September 2025 and the second after 1 July 2026, to install EMAS at the end of Runway 27.