第 2 部分的破土动工日期为 2018 年 2 月 23 日。Metro[3][5][6] 2026 年 11 月 19 日的员工报告预计将于 2027 年秋季基本完工,取代之前的 2027 年春季里程碑;11 月 30 日是预计的赛季结束日,而不是承诺的开幕日。客运服务时间尚未确定。
Primary staff report states substantial completion shifts Spring to Fall 2027; existing $2,574,969,299 LOP and requested $296m increase, not an adopted action.[1]
Metro's[5][6] fact sheet: Section 2 is 2.59 miles with Beverly Dr and Century City stations, operations Spring 2027; life-of-project budget for all three sections $9.7 billion.
Section 2 groundbreaking February 23, 2018; tunneling completed April 2, 2024; Section 1 opened May 8, 2026; Sections 2 and 3 listed for 2027.[1]
Metro's[3][6] forecasted schedule table: Section 2 construction 2018-2026, operations Spring 2027; Section 3 operations Fall 2027; Section 1 opened May 8, 2026.
有遗漏或错误吗?用你自己的话说明:能佐证此图钉的链接、不同的开始或结束日期及理由,或缺失、有误的信息。AI 会对照此图钉的来源进行核实,搜索更好的来源,并添加任何支持你说法的页面。图钉自身的来源仍然最重要。AI 也会查看图片:显示的是别的东西或显示效果差的图片会被移到后面或替换。
2.6 miles (4.2 km) to Century City
“which will extend trackage 2.6 miles (4.2 km) further to Century City”
Fall 2027, shifted from Spring 2027
“The revised forecast for substantial completion shifts from Spring 2027 to Fall 2027.”
Section 1 opened May 8, 2026; Section 2 under construction
“Construction was completed in early 2026, and Section 1 opened on May 8, 2026.”
Section 2 official groundbreaking ceremony
“the official Section 2 groundbreaking ceremony took place on February 23, 2018”
Section 1 opened
“Section 1 opened on May 8, 2026”
Section 2 substantial completion forecast; not passenger opening
“The revised forecast for substantial completion shifts from Spring 2027 to Fall 2027.”
原标题: Metro’s D Line Section 2 Substantial Completion Forecast Moves to Fall 2027
Metro 2026 年 11 月 19 日的工作人员报告列出了现有第 2 部分项目生命周期预算为 2,574,969,299 美元,并要求另外提供 2.96 亿美元,使拟议总额达到 2,870,969,299 美元。议程记录没有发布最终行动,因此较高的金额是请求,而不是经过验证的批准预算。报告称,在承包商索赔得到解决后,实质性竣工工作已从 2027 年春季推迟到秋季;实质性完成与客运服务不同。[2]
该地图点是星座大道和星光大道的估计车站区域锚点,而不是经过验证的入口。