Oliver County Zoning Board Votes Against Base Electron Power Plant
- On 24 September 2026 the Oliver County Planning and Zoning Commission took up again the Base Electron applications it had tabled in August: rezoning about 312 acres from agricultural to industrial, conditional use permit #1105, building permit #1106 and temporary use permit #1107 for construction facilities[2][5].
- All four motions to approve failed 2-3, according to a summary of the county's recording of the meeting; the members voting no mainly cited unresolved questions about water, natural gas supply, the electrical interconnection and the response to local residents' concerns[1][4].
- The planning and zoning board only recommends: the applications go on to the Oliver County Commission, which can follow the recommendation, overrule it or put off its decision[4].
- The plant is the 1,200 MW Missouri Bend Energy Center that Babcock & Wilcox is to build for Base Electron to power Applied Digital's AI data centres, with construction planned from the second quarter of 2027 and operation in the second half of 2030[3].
- In August the board had named road access, water use and the plant's location on the property as issues needing more information[5].
参考资料 5可信度 83%总体可信度: 83%该图钉的来源和参考资料对其日期的支持程度。包括来源在内的 5 份资料对图钉开始和结束时间支持程度的加权平均;资料每比最新的一份旧 180 天,权重减半显示所有可信度不低于 75% 的图钉
第一项始终是图钉的来源。总体可信度是各份资料对上方所用开始和结束时间支持程度的加权平均;资料每比最新的一份旧 180 天,权重减半。
- [1]90%facebook.com/100088537675086/videos/1713421796397791facebook.com· 发布于 2026年9月28日· 开始 2026年9月25日 ✓· 占评分 21%
Stated as done, per the county's recording of its 24 September 2026 Planning & Zoning meeting as summarised on r/babcockwilcox: "All four motions to approve failed by a 2-3 vote"; the county's agenda sets the Base Electron rezoning hearing for 7:10 PM that day.
- [2]90%Oliver County: September 24, 2026 Planning & Zoning Meeting agendaolivercountynd.org· 添加于 2026年9月28日· 开始 2026年9月24日· 占评分 21%
The county's agenda: 7:10 PM zoning map amendment hearing for Base Electron's 312 acres in Sections 25 and 36, Township 142, Range 85, from agricultural to industrial for a natural gas power plant, and 7:30 PM conditional use permit #1105, both tabled from the previous meeting.[1]
- [3]80%Missouri Bend Energy Center project brochure (Base Electron)wdeawebsite.blob.core.windows.net· 添加于 2026年9月28日· 占评分 21%
Base Electron's brochure: 1,200 MW near Center, construction from the second quarter of 2027 led by Babcock & Wilcox, completion in the second half of 2030.[1]
- [4]72%Quick Summary - Base Electron, September 24, 2026 (r/babcockwilcox)reddit.com· 发表于 2026年9月25日· 开始 2026年9月24日· 占评分 20%
A shareholder's summary of the county's recording: the rezoning, conditional use permit #1105, building permit #1106 and temporary use permit #1107 each failed 2-3; opponents cited water, natural gas, the grid connection and residents' concerns; P&Z only recommends and the commissioners decide.[1]
- [5]85%Oliver County Delays Power Plant Decisions (WDEA)ndenergy.org· 发表于 2026年8月28日· 开始 2026年8月27日· 占评分 18%
WDEA on the 27 August meeting where the board tabled the rezoning and conditional use permit, naming road access, water use and the plant's location on the property as open issues.[1]