Village of Plover and towns of Grant, Plover and Buena Vista, Portage County, Wisconsin (Plover village point used for coordinates)Doral Renewables
ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins71% CONFIDENCEOverall confidence: 71%How well the pin's source and references back up its dates.Weighted average of how firmly 5 references, the source included, support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins from 50% to 74% confidence
PSC final decision (16 Jan 2025): construction anticipated to start Q1 2025 and finish by the end of 2028; Doral's own page now says construction is expected to begin in 2026, so the date may slip. Cleanview[3] lists December 2028.
Doral Renewables' Vista Sands Solar near Plover in Portage County, Wisconsin won PSC approval for 1,315.6 MWac of solar and a 300 MW battery (Doral's page says 1,200 MW), with Doral citing nearly $2 billion of capital investment and operation targeted by end of 2028.
BLM land near Amargosa Valley, Nye County, Nevada (federal dashboard centroid)Leeward Renewable Energy
ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins60% CONFIDENCEOverall confidence: 60%How well the pin's source and references back up its dates.Weighted average of how firmly 5 references, the source included, support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins from 50% to 74% confidence
Cleanview lists expected operation December 2028; the federal dashboard puts completion of environmental review and permitting at 6 December 2027 after three schedule extensions, so no developer-stated operating date exists and 2028 is an estimate that may slip. Dashboard re-read 16 Oct 2026: review and permitting completion 12/06/2027, estimated cost 1,000,000,000 USD.[1]
Leeward Renewable Energy's Silver Star Solar 1 would be a 650 MW AC solar plant (517 MW in Cleanview's tracker) with a 650 MW battery on about 3,005 acres of BLM land near Amargosa Valley, Nye County, Nevada, with a federal estimated project cost of 1 billion USD.
ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins50% CONFIDENCEOverall confidence: 50%How well the pin's source and references back up its dates.Weighted average of how firmly 1 reference, the source included, supports the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins from 50% to 74% confidence
ClinicalTrials.gov[1] lists 2028-12-11 as the estimated primary completion date; a sponsor's estimate, and trials of this size routinely slip.
Pfizer's phase 3 trial of C.Difficile Vaccine in clostridoides difficile associated disease reaches primary completion, the point at which the last participant's primary outcome is measured. The trial enrolled 32,500 participants. The purpose of the study is to learn about how effective, safe, and tolerable the Clostridioides difficile (C. difficile) vaccine is in decreasing the number of C. difficile infections (pCDI) in adults 65 years of age or older. The participants will receive either the C. difficile vaccine or placebo (saline). A placebo does not contain any active ingredients. The vaccines will be given as a shot into the upper arm muscle. This study looks at the number of diarrhea (loose stools) events related to a C. difficile infection, so the length of the study can change. If these events happen quickly, the study may finish sooner; if they happen slowly, it could take longer. Sometimes, the study might stop early if the vaccine clearly does not work. Participants will stay in the study until enough events have occurred to answer the main question.
ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins50% CONFIDENCEOverall confidence: 50%How well the pin's source and references back up its dates.Weighted average of how firmly 1 reference, the source included, supports the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins from 50% to 74% confidence
ClinicalTrials.gov[1] lists 2028-12-30 as the estimated primary completion date; a sponsor's estimate, and trials of this size routinely slip.
Pfizer's phase 3 trial of PG4 in pneumococcal disease reaches primary completion, the point at which the last participant's primary outcome is measured. The trial enrolled 2,400 participants. The purpose of this study is to learn about the safety of a new pneumococcal vaccine and how the new pneumococcal vaccine helps to fight against germs that can cause pneumonia (lung infections), meningitis (brain infections), and otitis media (ear infections) in infants when compared to the pneumococcal vaccine that is currently in use, 20vPnC (Prevnar 20®). This study will test if the new pneumococcal vaccine is as safe as the one that is currently in use. This new vaccine can possibly provide additional protection against germs that cause pneumococcal disease that are not included in the vaccines that are currently given to infants. Pneumococcal disease includes a variety of infections caused by a specific germ, Streptococcus pneumoniae. There are two groups in this study. All participants will be assigned to one of the two groups.
Near Bush Knob Cemetery, FM 923, Throckmorton County, Texas (Bush Knob 69 kV interconnection)Solvent Energy
ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins64% CONFIDENCEOverall confidence: 64%How well the pin's source and references back up its dates.Weighted average of how firmly 4 references, the source included, support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins from 50% to 74% confidence
ERCOT queue 25INR0558 lists a commercial operation date of 30 December 2028 (Cleanview[3]: December 2028); the developer has published no date, and the county's November 2024 rescission of the abatement makes the date uncertain.
Solvent Energy's Ayass BESS is a 51 MW (ERCOT: 51.28 MW) battery in Throckmorton County, Texas on ERCOT queue 25INR0558; the county approved a tax abatement agreement 5-0 on 8 July 2024 and voted 5-0 on 12 November 2024 to rescind it, and no cost has been published.
JASM, Haramizu, Kikuyo, Kikuchi County, Kumamoto Prefecture 869-1103, JapanTSMC
ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins12 months late71% CONFIDENCEOverall confidence: 71%How well the pin's source and references back up its dates.Weighted average of how firmly 6 references, the source included, support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins from 50% to 74% confidence
Only a year is given: Taiwan's MOEA says the fab is "scheduled to start installing equipment and come online in 2028", and C.C. Wei said on the 16 April 2026 call that "commercial production is scheduled to begin in 2028" - so the year's last day, estimated.[1]
JASM's second fab in Kikuyo, Kumamoto - switched from 6nm-class chips to TSMC's 3nm process - is due to start volume production in 2028 at 15,000 12-inch wafers a month, making Japan's first 3nm chips about a year after the end-2027 start TSMC first promised.
ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins65% CONFIDENCEOverall confidence: 65%How well the pin's source and references back up its dates.Weighted average of how firmly 2 references, the source included, support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins from 50% to 74% confidence
Rio Tinto[1] expects Oyu Tolgoi to produce around 500,000 tonnes of copper a year on average from 2028 to 2036 across the open pit and underground. Only the year is given, so the pin takes its last day.
Rio Tinto's Oyu Tolgoi in the Gobi is expected to average around 500,000 tonnes of copper a year from 2028, on its way to being the world's fourth-largest copper mine.
McDonnell Boulevard, Hazelwood, Saint Louis County, Missouri, 63042, United StatesBoeing
ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins62% CONFIDENCEOverall confidence: 62%How well the pin's source and references back up its dates.Weighted average of how firmly 3 references, the source included, support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins from 50% to 74% confidence
Air & Space Forces Magazine (22 Sept 2025): 'The first F-47 Next-Generation Air Dominance fighter will be ready to fly by 2028', Gen. Allvin said; the pin takes the last day of 2028.[1]
The first Boeing F-47, the US Air Force's sixth-generation air-dominance fighter, was already being built in September 2025, and Air Force chief of staff Gen. David Allvin said it would be ready to fly by 2028.
Delta Blues Advanced Power Station, Washington County, MS, United States
ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins95% CONFIDENCEOverall confidence: 95%How well the pin's source and references back up its dates.Weighted average of how firmly 2 references, the source included, support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins at 75% confidence or better
Published target: 2028. Construction is documented, but this future completion/operation milestone is estimated. The date is a year/month-end timeline marker and is not a confirmed exact opening day. Source: https://www.entergy[2].com/blog/delta-blues-reaches-important-milestone-in-construction
Estimated operation/completion target: 2028. 754 MW generating capacity; About USD 1.2 billion published project cost. Under construction.
ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins62% CONFIDENCEOverall confidence: 62%How well the pin's source and references back up its dates.Weighted average of how firmly 3 references, the source included, support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins from 50% to 74% confidence
A target, per the source[1]: the tower "is set for completion in December 2028", with no official opening date yet announced.
Dubai developer Muraba and Pritzker Prize-winner RCR Arquitectes are building Muraba Veil, a 380m tower just 22.5m wide wrapped in a porous steel mesh, among the world's skinniest skyscrapers.
Hyundai Motor Group Metaplant America, Ellabell, Georgia, USAHyundai Motor Group
ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins68% CONFIDENCEOverall confidence: 68%How well the pin's source and references back up its dates.Weighted average of how firmly 4 references, the source included, support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins from 50% to 74% confidence
The release says only "Atlas to be deployed at HMGMA by 2028 for sequencing tasks", so this takes the last day of that year as the bound the wording gives.[1]
Hyundai's CES 2026 robotics strategy commits Boston Dynamics' Atlas to parts-sequencing work at Metaplant America in Georgia by 2028, after the humanoids are trained at the group's Robot Metaplant Application Center; assembly tasks are to follow by 2030.
ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins67% CONFIDENCEOverall confidence: 67%How well the pin's source and references back up its dates.Weighted average of how firmly 3 references, the source included, support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins from 50% to 74% confidence
The official website only gives a 2028 theatrical release, so the pin sits at the end of that year.[1]
Sword Art Online returns to cinemas with Integral Domain, an original movie from A-1 Pictures and Psyde Kick Studio that brings Kirito and Asuna back, due in Japanese theaters in 2028.
Lone Star Power Station, San Jacinto County, TX, United States
ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins95% CONFIDENCEOverall confidence: 95%How well the pin's source and references back up its dates.Weighted average of how firmly 6 references, the source included, support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins at 75% confidence or better
Published target: 2028. Construction is documented, but this future completion/operation milestone is estimated. The date is a year/month-end timeline marker and is not a confirmed exact opening day. Source: https://www.entergy[4][5][6].com/news/entergy-texas[2]-breaks-ground-legend-and-lone-star
Estimated operation/completion target: 2028. 453 MW generating capacity; About USD 799 million published project cost. Under construction.
ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins56% CONFIDENCEOverall confidence: 56%How well the pin's source and references back up its dates.Weighted average of how firmly 3 references, the source included, support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins from 50% to 74% confidence
A target year, per SPA's[1] copy of Aramco's[3] 30 June 2024 release: the expansion 'will ... raise its total capacity by an additional 3.15 billion standard cubic feet per day (bscfd) by 2028' - a bare year, so its last day.
Around 4,000 km of new pipelines and 17 compression trains are to add 3.15 billion cubic feet a day to the network that carries gas across Saudi Arabia, built under 15 contracts worth about $8.8 billion.
ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins95% CONFIDENCEOverall confidence: 95%How well the pin's source and references back up its dates.Weighted average of how firmly 4 references, the source included, support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins at 75% confidence or better
Published target: Early 2028 electricity generation. Construction is documented, but this future completion/operation milestone is estimated. The date is a year/month-end timeline marker and is not a confirmed exact opening day. Source: https://wapda.gov.pk[3][4]/mohmand-dam-hydropwer-project/
Estimated operation/completion target: Early 2028 electricity generation. 800 MW generating capacity; About USD 2.2496 billion published project cost. Under construction.
ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins50% CONFIDENCEOverall confidence: 50%How well the pin's source and references back up its dates.Weighted average of how firmly 1 reference, the source included, supports the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins from 50% to 74% confidence
The airport's own project page says the new Terminal 1 opens "19 [gates] in 2025 and the remaining 11 by 2028", giving a year rather than a day, so it sits at the end of that year.[1]
The second phase of San Diego International Airport's $3.8 billion Terminal 1 replacement adds the last 11 gates, two lounges, nine restaurants and three shops. Phase 1 opened with 19 gates in 2025 and phase 2 went to work that October.
Legend Power Station, Jefferson County, TX, United States
ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins95% CONFIDENCEOverall confidence: 95%How well the pin's source and references back up its dates.Weighted average of how firmly 5 references, the source included, support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins at 75% confidence or better
Published target: 2028. Construction is documented, but this future completion/operation milestone is estimated. The date is a year/month-end timeline marker and is not a confirmed exact opening day. Source: https://www.entergy[3][4][5].com/news/entergy-texas-breaks-ground-legend-and-lone-star
Estimated operation/completion target: 2028. 754 MW generating capacity; About USD 1.6 billion published project cost. Under construction.
Jefferson County, Arkansas, United States (White Bluff substation area)Entergy
ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins64% CONFIDENCEOverall confidence: 64%How well the pin's source and references back up its dates.Weighted average of how firmly 3 references, the source included, support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins from 50% to 74% confidence
Interconnection.fyi[3] (EIA data) lists a proposed in-service date of 1 January 2029; Entergy's contract with Google ramps to 600 MW by October 2029 and one outlet reports Q4 2028 completion.
Entergy Arkansas is building a 600 MW solar array with a 350 MW battery system in Jefferson County, Arkansas, an estimated 1,602M USD, partly paid by Google to power its West Memphis data center.
NE 30th Avenue and NE Evergreen Road, Hillsboro, Washington County, Oregon 97124, United StatesAligned Data Centers
ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins68% CONFIDENCEOverall confidence: 68%How well the pin's source and references back up its dates.Weighted average of how firmly 5 references, the source included, support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins from 50% to 74% confidence
Baxtel[3] lists "Year Planned: 2029" and notes the building was halted by the 27 July 2026 moratorium; DCD says "Timelines for development were not shared" and Cleanview[4] gives no year.
Aligned Data Centers filed a pre-application on 27 July 2026 for PDX-02, the 36 MW (50.4 MW facility power in Cleanview) second building of its 108 MW Hillsboro, Oregon campus, hours before the city council enacted a 120-day moratorium; no cost has been published.
ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins50% CONFIDENCEOverall confidence: 50%How well the pin's source and references back up its dates.Weighted average of how firmly 1 reference, the source included, supports the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins from 50% to 74% confidence
The Ministry of Health says the campus "has commenced construction works and will open progressively from 2029", giving a year rather than a day.[1]
The Eastern General Hospital Campus begins opening on a site next to Bedok North MRT station, bounded by Bedok Reservoir Road and Bedok North Road. It pairs an acute general hospital offering emergency, inpatient and specialist outpatient services with a co-located community hospital for rehabilitation and sub-acute care, relieving Changi General Hospital in Singapore's east.
About three miles south of Broadview, Yellowstone County, Montana, United States (approximate: Broadview town centroid offset by the reported distance; the parcel address is not published)Quantica Infrastructure
ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins75% CONFIDENCEOverall confidence: 75%How well the pin's source and references back up its dates.Weighted average of how firmly 6 references, the source included, support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins at 75% confidence or better
NonStop Local Billings (21 May 2026): "Quantica hopes to have its first building operational in 2029"; no month is given.[1]
Quantica Infrastructure plans a 5,000-acre data center campus about three miles south of Broadview, Yellowstone County, Montana, announced at 500 MW expandable to 1,000 MW (company) and now backed by a May 2026 request to NorthWestern Energy for up to 7,235 MW; no cost or tenant has been published, and the project faces a county lawsuit over a ballot initiative and a land-deal suit.
Near Wilson, Mississippi County, Arkansas, United States (town centroid; project site approximate)Cypress Creek Renewables
ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins70% CONFIDENCEOverall confidence: 70%How well the pin's source and references back up its dates.Weighted average of how firmly 5 references, the source included, support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins from 50% to 74% confidence
Google (14 July 2026): the full three-phase project will be "fully operational in 2029"; Cypress Creek said all phases enter service by 2029. Cleanview's[2] three rows give August 2028 (phase 1), July 2029 and July 2030, so phase 3 may slip past 2029.
Cypress Creek Energy's three-phase Steel River Energy Center in Mississippi County, Arkansas (about 815 MWdc of solar per phase, 2.45-2.5 GWdc total, 2.9 GWh and 720 MW of battery) broke ground on 14 July 2026 with a Google power purchase agreement for the first two phases and a total capital cost above 4.5 billion USD.
Alto and Willow Creek townships near Steward, Lee County, Illinois (village of Steward used for coordinates; county-level)TerraForm Power
ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins61% CONFIDENCEOverall confidence: 61%How well the pin's source and references back up its dates.Weighted average of how firmly 4 references, the source included, support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins from 50% to 74% confidence
TerraForm[1], 2 Feb 2026: "Phase 1 construction expected to begin in 2027 with commercial operation in 2029"; phase 2 construction 2028, operation 2030. Cleanview[2] lists December 2029 for the 1,200 MW row.
TerraForm Power bought the Steward Creek Solar project from Hexagon Energy in February 2026; Lee County, Illinois approved two 600 MW phases (1,200 MW; TerraForm cites 1.56 GW) for PJM, with phase 1 operation targeted for 2029 and no cost published.
Phoenix Sky Harbor International Airport, 3400 E Sky Harbor Blvd, Phoenix, AZ 85034City of Phoenix
ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins60% CONFIDENCEOverall confidence: 60%How well the pin's source and references back up its dates.Weighted average of how firmly 2 references, the source included, support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins from 50% to 74% confidence
The airport's own schedule lists "Construction 2029 - 2033" with no start date, so the pin uses the start of 2029. Completion: Phoenix Sky Harbor[1][2] release, 21 Sep 2026: "Construction could potentially begin in late 2029 with an opening in late 2033" (late 2033 read as by the end of 2033).
Sky Harbor's West Terminal, the airport's first new terminal since Terminal 4 opened in 1990, is scheduled to go into construction in 2029 and open in 2033, with the number of concourses and gates still to be decided. The airport puts the likely cost at around $4.5 billion, paid for with passenger facility charges, bonds and airport funding rather than tax dollars.
ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins58% CONFIDENCEOverall confidence: 58%How well the pin's source and references back up its dates.Weighted average of how firmly 2 references, the source included, support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins from 50% to 74% confidence
Mangum Economics (23 Jul 2026) schedules construction jobs from 2027 to 2033; Cleanview dates the first two buildings to 2029 and the last to 2033; Aligned has not published a day.[1]
Aligned Data Centers proposes Project Star, a 3.2 million sq ft data center campus at Coal City in Grundy County, Illinois, about 864 MW of facility power and 15.1B USD of total investment including the tenant's equipment.
22243 Stottlemeyer Rd NE, Poulsbo, WA 98370BrightNight
ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins69% CONFIDENCEOverall confidence: 69%How well the pin's source and references back up its dates.Weighted average of how firmly 4 references, the source included, support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins from 50% to 74% confidence
BrightNight publishes no schedule; the 1 February 2029 operating date comes from EIA-860M (plant 68366, generator AGAT) as listed by Cleanview[3], and an earlier tracker listing said December 2027, so the date is only an estimate.
BrightNight is proposing the Agate Storage Project, a 150 MW / 600 MWh lithium-ion battery (about 170 MW in the county SEPA filing) next to Puget Sound Energy's Foss Corner Substation near Poulsbo, Washington; no cost or schedule is published and Kitsap County's battery moratorium runs to 7 December 2026.
ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins56% CONFIDENCEOverall confidence: 56%How well the pin's source and references back up its dates.Weighted average of how firmly 3 references, the source included, support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins from 50% to 74% confidence
Given as a target, not a fixed date, per en.wikipedia.org[1]: "…and construction in July 2023, with the expected completion and first light set for March 2029.[13][…"
A 39-metre segmented mirror in Chile's Atacama, collecting more light than all existing 8-10 metre telescopes combined. Estimated date.
Reichstag building, Platz der Republik 1, Berlin, Germany
ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins60% CONFIDENCEOverall confidence: 60%How well the pin's source and references back up its dates.Weighted average of how firmly 3 references, the source included, support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins from 50% to 74% confidence
No date has been set. Kalshi[1] dates its event to March 25, 2029, the last day the Basic Law's 46-to-48-month window allows after the current Bundestag first sat on March 25, 2025; a snap election would come earlier.
Kalshi
Polymarket
The Bundestag elected in February 2025 first sat on March 25, 2025, and the Basic Law requires a new election 46 to 48 months later - March 25, 2029 at the latest. On 20 September 2026 Kalshi's winner market had the AfD at 85% and the CDU/CSU at 12%.
Duane Arnold Energy Center, Linn County, Iowa, United StatesNextEra Energy
ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins81% CONFIDENCEOverall confidence: 81%How well the pin's source and references back up its dates.Weighted average of how firmly 7 references, the source included, support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins at 75% confidence or better
Operator targets restart by Q1 2029, conditional on regulatory approvals. March 31 is an estimated quarter boundary.[1]
NextEra aims to bring the 615 MW Duane Arnold Energy Center near Palo, Iowa, back online around the end of 2028 or early 2029 after the Department of Energy closed a loan of up to $1.9 billion on 8 September 2026; Google has contracted to buy its output for 25 years.
ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins68% CONFIDENCEOverall confidence: 68%How well the pin's source and references back up its dates.Weighted average of how firmly 2 references, the source included, support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins from 50% to 74% confidence
ESO[1][2] states the ELT "is now set to make its first test observations at the beginning of 2029, with 'telescope first light' expected in March 2029". Only the month is given, so the pin takes its last day.
ESO's 39-metre Extremely Large Telescope takes its first test observations from Cerro Armazones in March 2029, with scientific first light following in December 2030.
DELAYEDDate confidence: DELAYEDThe date has movedHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all DELAYED pins4.5 years late56% CONFIDENCEOverall confidence: 56%How well the pin's source and references back up its dates.Weighted average of how firmly 3 references, the source included, support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins from 50% to 74% confidence
Date has moved, per the source[1]: "telescope first light" is "now planned for March 2029," after "several of the telescope contracts suffered delays."
The European Southern Observatory's Extremely Large Telescope, being built atop a Chilean mountain by 16 partner nations, is now targeting first light in March 2029 after repeated delays.
Rowesville Road, Orangeburg County, South Carolina 29115, United StatesFerrero
ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins66% CONFIDENCEOverall confidence: 66%How well the pin's source and references back up its dates.Weighted average of how firmly 3 references, the source included, support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins from 50% to 74% confidence
Ferrara[1]: 'The first production lines are expected to begin operations in the first quarter of 2029, with the full facility opening later that year' - pinned to the quarter's last day.
The first production lines of Ferrara Candy Company's $675 million, 750,000 sq ft plant in Orangeburg County, South Carolina are due to start in the first quarter of 2029, with the full facility opening later that year.
ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins50% CONFIDENCEOverall confidence: 50%How well the pin's source and references back up its dates.Weighted average of how firmly 1 reference, the source included, supports the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins from 50% to 74% confidence
The airport's own project page says the concourse is "scheduled for completion by Spring 2029" - a season, not a fixed day, so the pin uses the start of that spring.[1]
MIA is building a three-level Concourse K with six domestic gates, new baggage handling, a ground support equipment maintenance facility and airfield work, the first new concourse of its $9 billion modernisation programme. Construction broke ground in mid-2025.
ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins50% CONFIDENCEOverall confidence: 50%How well the pin's source and references back up its dates.Weighted average of how firmly 1 reference, the source included, supports the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins from 50% to 74% confidence
Mitsui Fudosan's[1] release gives "Scheduled opening: First half of 2030s or later (advance opening of facility in fiscal 2029)", so the pin sits on 1 April 2029, the first day of that fiscal year.
Mitsui Fudosan's consortium is rebuilding the 190,000 sq m former Tsukiji fish market site in Chuo City as nine buildings totalling about 1,170,000 sq m, including an all-weather multifunctional venue for roughly 50,000 people, a theatre hall, a culinary centre and a waterbus terminal. The whole scheme is costed at about 900 billion yen.
UNVERIFIEDDate confidence: UNVERIFIEDNo wording about the date was foundHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all UNVERIFIED pins59% CONFIDENCEOverall confidence: 59%How well the pin's source and references back up its dates.Weighted average of how firmly 3 references, the source included, support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins from 50% to 74% confidence
A 340-metre asteroid passes about 32,000 km from Earth, closer than geostationary satellites and visible to the naked eye from Europe and Africa.
Freestone County, Texas (EIA-860M site point near the Big Brown-Jewett 345 kV line)Avant Prairie ESS LLC
ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins71% CONFIDENCEOverall confidence: 71%How well the pin's source and references back up its dates.Weighted average of how firmly 5 references, the source included, support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins from 50% to 74% confidence
ERCOT queue 27INR0316 (via InfraSure[2][3]) lists a proposed commercial operation date of 16 April 2029; EIA-860M lists 1 July 2029; the Freestone County Times report of the abatement says "projected to be complete in 2028". The InfraSure page also shows an inconsistent 1 July 2027 in one section.
Avant Prairie ESS LLC (OCI Energy) is developing a battery energy storage facility in Freestone County, Texas that the county tax abatement describes as 16 MW on 36 acres (complete 2028, ,097 PILOT) and that ERCOT queue 27INR0316 lists at 201.72 MW (EIA-860M: 200 MW); OCI Energy officially lists the 200 MW Avant Prairie project in its development portfolio.
ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins50% CONFIDENCEOverall confidence: 50%How well the pin's source and references back up its dates.Weighted average of how firmly 1 reference, the source included, supports the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins from 50% to 74% confidence
The Election Commission has not announced a schedule. Kalshi's[1] event ticker is dated April 30, 2029, which matches the 18th Lok Sabha's term ending in June 2029 and the spring polling India has used since 2014; its contracts stay open a year past that.
Kalshi
The 18th Lok Sabha's five-year term runs to June 2029, so India's next general election falls in the spring of that year. Kalshi dates its market to April 30, 2029, and on 20 September 2026 it had Narendra Modi at 51%, Yogi Adityanath at 19% and Rahul Gandhi at 6.5%.