Fortress Project Site, County Road 28, Southeast of Brush, Morgan County, CO 80723Aypa Power (Blackstone)
ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins75% CONFIDENCEOverall confidence: 75%How well the pin's source and references back up its dates.Weighted average of how firmly 4 references, the source included, support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins at 75% confidence or better
The saved date is an estimated tracking/commissioning target unless noted; EIA[2] monthly actual or planned dates do not establish an exact day. Status follows the exact unit’s reported physical stage.
The 150MW Fortress 1 generator 2 battery has regulatory approvals pending and is expressly not under construction. The separate 49.9MW generator and the larger solar/hybrid park are excluded.
ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins52% CONFIDENCEOverall confidence: 52%How well the pin's source and references back up its dates.Weighted average of how firmly 3 references, the source included, support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins from 50% to 74% confidence
MISO interconnection queue studies and local industrial siting authorizations set commercial operation for March 2028.[1]
The Huttig Energy Storage Project is a 100 MW / 400 MWh 4-hour battery energy storage system located near Huttig and Strong in Union County, southern Arkansas. Sited along the Huttig SS to Strong SS 115 kV transmission corridor within MISO, the containerized lithium iron phosphate (LFP) storage facility delivers essential grid resilience, frequency support, and peak-shaving capacity for regional forest products processing and manufacturing loads.
State Route 131 & Oyster River Road, Warren, Knox County, ME 04864Swift Current Energy
ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins75% CONFIDENCEOverall confidence: 75%How well the pin's source and references back up its dates.Weighted average of how firmly 4 references, the source included, support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins at 75% confidence or better
Maine[4] DEP Site Location of Development Act Permit #L-29188-26-A-N and Swift Current Energy[1] schedules target commercial operation in March 2028.
Swift Current Energy (in partnership with original developer Glenvale Solar) is constructing the 75 MWac Warren Meadow Solar Project across 485 acres in the Town of Warren, Knox County, Maine. Permitted by the Maine Department of Environmental Protection under Site Location of Development Act Permit #L-29188-26-A-N and approved by the Warren Planning Board, the utility-scale solar complex connects to Central Maine Power's transmission corridor, supplying clean power to the ISO New England grid.
ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins75% CONFIDENCEOverall confidence: 75%How well the pin's source and references back up its dates.Weighted average of how firmly 3 references, the source included, support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins at 75% confidence or better
Commercial operation targeted for March 2028 based on North Carolina Utilities Commission filings and Washington County conditional use permit.[1]
The Macadamia Solar Energy Facility is a 375 MWac utility-scale photovoltaic generation facility situated across coastal plain acreage near Plymouth in Washington County, North Carolina. Developed by EDF Renewables to interconnect with the PJM Interconnection via Dominion Energy's transmission system, the installation generates bulk zero-carbon energy for the Mid-Atlantic while delivering long-term county tax revenues.
Douglas Clean Energy Storage Center, US Highway 275 & State Highway 31 Corridor, Elkhorn, Douglas County, NE 68022
ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins95% CONFIDENCEOverall confidence: 95%How well the pin's source and references back up its dates.Weighted average of how firmly 3 references support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins at 75% confidence or better
2028-03-01 is the interconnection record’s requested in-service date, not a verified opening or commercial-operation day.
GEN-2024-372 is a 250 MW battery storage interconnection request in Douglas, NE. The grid operator lists its queue status as DISIS STAGE. The requested in-service date is 2028-03-01; this is a planning date.
ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins52% CONFIDENCEOverall confidence: 52%How well the pin's source and references back up its dates.Weighted average of how firmly 3 references, the source included, support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins from 50% to 74% confidence
Public Service Commission of Wisconsin filings and MISO generator interconnection queue milestone studies set commercial operation for March 2028.[1]
The Granville Energy Storage Project is a 300 MW / 1,200 MWh 4-hour battery energy storage facility located near Granville and Brown Deer in northwestern Milwaukee County, Wisconsin. Connecting directly into American Transmission Company's (ATC) Granville 345 kV Substation in MISO, the utility-scale lithium-ion battery system delivers high-reliability capacity, absorbs surplus regional renewable power, and provides essential grid resilience for the Greater Milwaukee metropolitan area.
ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins50% CONFIDENCEOverall confidence: 50%How well the pin's source and references back up its dates.Weighted average of how firmly 1 reference, the source included, supports the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins from 50% to 74% confidence
ClinicalTrials.gov[1] lists 2028-03-13 as the estimated primary completion date; a sponsor's estimate, and trials of this size routinely slip.
Sanofi's phase 3 trial of MenQuadfi in meningococcal infection reaches primary completion, the point at which the last participant's primary outcome is measured. The trial enrolled 4,568 participants. The purpose of this study is to describe the safety and immunogenicity of MenACYW conjugate vaccine compared with locally-licensed meningococcal vaccines in healthy infants and toddlers in China. Study details include: * Study duration (including 6-month safety follow-up after the last dose): * Cohort I (Groups 1 and 2): approximately 211 or 271 days (approximately 7 or 9 months) * Cohort II (Groups 3 and 4): up to 18 months * Cohort III (Groups 5 and 6): up to 21 months * Cohort III (Group 7): approximately 16 months * Vaccination Visits Period: * Cohort I (Groups 1 and 2): a 2-dose vaccination at V01 (D01) and V02 (D31) or V03 (D91). Two blood samples are collected pre-vaccination (D01) and 30 days post the 2nd dose of vaccination (D61 or D121).
ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins78% CONFIDENCEOverall confidence: 78%How well the pin's source and references back up its dates.Weighted average of how firmly 5 references, the source included, support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins at 75% confidence or better
Estimated: metro manager Leonidas Narváez gives March 14, 2028 in October 9 reporting; September reporting quoted March 15. The newer direct operator statement is used, retaining the conflict.[1]
After more than 80 years of proposals, Bogotá's first metro line, an elevated 24km driverless railway, is targeted to carry its first passengers in 2028.
ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins79% CONFIDENCEOverall confidence: 79%How well the pin's source and references back up its dates.Weighted average of how firmly 5 references, the source included, support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins at 75% confidence or better
Bogotá’s September 24, 2026 city update targets construction completion in September 2027, testing afterward and commercial operation in March 2028, citing March 15, 2028 for integrated passenger transfers. March 15 is a stated target, not an achieved opening; the former June marker is superseded.[1]
An elevated 24 km driverless line, the first metro for a capital that has debated building one since the 1940s. Estimated date.
SCHEDULEDDate confidence: SCHEDULEDGiven as scheduledHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all SCHEDULED pins63% CONFIDENCEOverall confidence: 63%How well the pin's source and references back up its dates.Weighted average of how firmly 4 references, the source included, support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins from 50% to 74% confidence
Mitsubishi Estate’s own construction-start release says Torch Tower and its substation building "are scheduled for completion at the end of March 2028", and its schedule table repeats "End of March 2028".[1]
The 385 m, 62-storey centrepiece of the Tokyo Torch district beside Tokyo Station holds offices, more than 100 shops, an events hall for 2,000 people and the first luxury rental flats in the Otemachi-Marunouchi-Yurakucho district. Construction started in September 2023.
US Highway 60 & Vicksburg Road, Brenda, La Paz County, AZ 85348
ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins95% CONFIDENCEOverall confidence: 95%How well the pin's source and references back up its dates.Weighted average of how firmly 1 reference supports the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins at 75% confidence or better
CAISO[1] queue 1402 current online target; planned, executed IA, not guaranteed COD.
CAISO queue 1402 lists Atlas Complex as an active hybrid request in La Paz County: 2,171 MW battery, 2,256 MW solar equipment and 3,200 MW net export. Current target is March 31, 2028; this is not a standalone battery with a verified $1.4B budget.
Royal Slope, off State Route 26, near Royal City, Grant County, Washington, United StatesClearway Energy Group
ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins95% CONFIDENCEOverall confidence: 95%How well the pin's source and references back up its dates.Weighted average of how firmly 3 references, the source included, support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins at 75% confidence or better
Grant PUD[2][3] October 2025 packet gives commencement no earlier than March 31, 2028. Preserve as an estimated lower-bound contract target, not a scheduled COD.
Clearway and Grant PUD signed 20-year solar and storage agreements for Royal Slope. Grant PUD’s packet specifies 260 MW solar and 260 MW / 1,040 MWh storage, with contractual commencement no earlier than March 31, 2028.
West Mount Whitney Avenue & South Derrick Avenue, Cantua Creek, Fresno County, CA 93608IP Darden I, LLC / Intersect
ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins95% CONFIDENCEOverall confidence: 95%How well the pin's source and references back up its dates.Weighted average of how firmly 3 references support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins at 75% confidence or better
August 2026 MCR Table 1 COD target March 31, 2028; first energization April 22, 2027 and CAISO[2] July 19, 2027 target differ.
CEC’s Darden page confirms 1,150 MW solar plus up to 1,150 MW / 4,600 MWh battery across approximately 9,500 acres, under construction. The August 2026 compliance report targets March 31, 2028 commercial operation, superseding the pin’s December 2029 claim.
ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins78% CONFIDENCEOverall confidence: 78%How well the pin's source and references back up its dates.Weighted average of how firmly 6 references, the source included, support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins at 75% confidence or better
Opening / first-lease date: projected opening recorded only to the month (March 2028) in The Bourne Apartments - Resident Meeting, April 6, 2026 (Pennrose[1][4] / Contour Housing Partners); the pin sits on the last day of that month. Not yet open: this is the projected opening, not a confirmed date. Confidence: medium. Existing occupied 205-unit property (Bourne tower 150 Smith St, reported built 1954; Kenney garden apts reported built 1965 - listing sites, low weight; prior LIHTC rehab late 1990s/PIS 2000 per Pennrose deck and LIHTC database). The only forward date is Pennrose/Contour's April 6, 2026 resident-meeting schedule: acquisition closing and construction start August 2026 (PILOT approved by Newburgh council 13 Apr 2026, 7-0), tenant-occupied rehab complete March 2028. This is rehab completion, not a first opening; if the pin needs an original opening date, 1954 (Bourne) is the only sourced figure but low confidence.
A proposed rehabilitation of 205 affordable homes at the Bourne and Kenney communities for households up to 60% AMI. The operator identifies Contour Housing Partners and Newburgh Housing Authority as the development team. Property information reviewed October 10, 2026.
ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins86% CONFIDENCEOverall confidence: 86%How well the pin's source and references back up its dates.Weighted average of how firmly 2 references, the source included, support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins at 75% confidence or better
Cleanview[2] lists the CAISO queue in-service date of 31 March 2028 for both the solar and storage entries; Intersolar reports the full Atlas Energy Park is expected by 2028.
Hanwha's Atlas Energy Park in La Paz County, Arizona, is queued at 2,256 MW of solar plus 2,171 MW of battery storage for 2028, part of a 2.8 GW and 5.7 GWh buildout; no total cost has been published.
Estimated: Monroe County, Michigan; approximate county context, exact J3994 battery parcel pending
ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins95% CONFIDENCEOverall confidence: 95%How well the pin's source and references back up its dates.Weighted average of how firmly 1 reference supports the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins at 75% confidence or better
April 1, 2028 is the queue’s requested inService date, not verified commissioning.
MISO lists J3994 as a 360 MW battery request at 18 MOROCCO 256583 in Monroe County, Michigan, with an April 1, 2028 in-service target. The active DPP-2026 request does not publish storage energy or developer ownership.
Garnet Clean Solar Energy Center, State Route 38 & Spook Woods Road Corridor, Conquest, Cayuga County, NY 13140NextEra Energy Resources
ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins95% CONFIDENCEOverall confidence: 95%How well the pin's source and references back up its dates.Weighted average of how firmly 3 references, the source included, support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins at 75% confidence or better
New York State Siting Board Article 10 compliance filings and NYISO interconnection schedules place the 200 MW Garnet Energy Center[1][2] in April 2028 commercial operation.
NextEra Energy Resources development of the Garnet Clean Solar Energy Center in the Town of Conquest, Cayuga County, New York. Certificated under New York Public Service Law Article 10 to deliver 200 MWac of solar power plus 20 MW of battery storage, the project connects to the NYPA Clay–Pannell 345 kV transmission line.
Estimated: Peoria County, Illinois; approximate county context, exact J2377 parcel pending
ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins95% CONFIDENCEOverall confidence: 95%How well the pin's source and references back up its dates.Weighted average of how firmly 1 reference supports the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins at 75% confidence or better
April 1, 2028 is the queue inService target, not confirmed COD.
MISO lists J2377 as an active 300 MW battery request in Peoria County, Illinois, at 7CLINTON–7BROKAW 345 kV. The Phase 2 request has an April 1, 2028 in-service target and Not Started post-GIA status.
ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins52% CONFIDENCEOverall confidence: 52%How well the pin's source and references back up its dates.Weighted average of how firmly 3 references, the source included, support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins from 50% to 74% confidence
Minnesota Public Utilities Commission clean energy docket filings and MISO interconnection agreements set commercial operation for April 2028.[1]
The Goodhue Energy Storage Project is a 330 MW / 1,320 MWh 4-hour battery energy storage system located near Red Wing in Goodhue County, Minnesota. Positioned along the high-voltage 345 kV transmission corridor connecting the NROC 3 and Prairie Island substations in MISO, the battery installation delivers massive dispatchable capacity, stores regional wind and solar generation, and reinforces transmission reliability for the Twin Cities and upper Mississippi River basin.
ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins75% CONFIDENCEOverall confidence: 75%How well the pin's source and references back up its dates.Weighted average of how firmly 4 references, the source included, support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins at 75% confidence or better
EIA’s[2] September 2026 preliminary inventory records a forecast operation month 2028-04. The first day of April 2028 is an estimated month-only display marker, not an exact opening day. The forecast does not prove physical completion and can change in later monthly inventories.
EIA’s September 2026 preliminary inventory identifies Broadleaf Solar, plant 68490, in Hartford County, CT, with 200 MW electrical generation nameplate. The listed stage is (L) Regulatory approvals pending. Not under construction. Operation is forecast for 2028-04; this is a preliminary survey estimate, not an achieved opening or capacity commitment.
ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins80% CONFIDENCEOverall confidence: 80%How well the pin's source and references back up its dates.Weighted average of how firmly 4 references, the source included, support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins at 75% confidence or better
Commercial operation projected for April 2028 based on Santee Cooper long-term resource plan filings and county permitting milestones.[1]
The Kingstree Georgetown Solar Project is a 249 MWac utility-scale photovoltaic generation facility located across managed timberland near Georgetown in Georgetown County, South Carolina. Financed and developed by Ingka Investments to supply clean renewable energy to the regional grid under power off-take arrangements with Santee Cooper, the project represents one of the largest single solar investments in the South Carolina Lowcountry.
Parlement européen - Europees Parlement, Rue de Trèves - Trierstraat, Quartier Léopold - Leopoldswijk, Ixelles - Elsene, Brussel-Hoofdstad - Bruxelles-Capitale, Région de Bruxelles-Capitale - Brussels Hoofdstedelijk Gewest, 1047, België / Belgique / BelgienEuropean Union
SCHEDULEDDate confidence: SCHEDULEDGiven as scheduledHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all SCHEDULED pins75% CONFIDENCEOverall confidence: 75%How well the pin's source and references back up its dates.Weighted average of how firmly 1 reference, the source included, supports the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins at 75% confidence or better
European Commission: the revised Waste Framework Directive 'enters into force today (16 Oct)' 2025, and 'Member States will have 20 months to transpose the revised Directive into national laws and 30 months to establish EPR schemes for textile and footwear products' - 30 months from 16 October 2025 is 16 April 2028.[1]
EU member states must have mandatory extended-producer-responsibility schemes for textiles and footwear running by 16 April 2028, 30 months after the revised Waste Framework Directive entered into force. The schemes make clothing and footwear makers fund the collection, sorting and recycling of textile waste.
US Highway 287 & Farm to Market Road 1151, Claude, Armstrong County, TX 79019Armstrong BESS, LLC
ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins95% CONFIDENCEOverall confidence: 95%How well the pin's source and references back up its dates.Weighted average of how firmly 1 reference supports the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins at 75% confidence or better
ERCOT[1] September 2026 row 728, 25INR0587 projected COD; estimate with no IA.
ERCOT’s September 2026 GIS report lists Zeus Armstrong BESS (25INR0587) in Armstrong County at 1,043.08 MW, with projected COD 2028-04-17. Study status is screening completed and FIS started, with no interconnection agreement; the former $950 million price is removed.
US Highway 287 & Farm to Market Road 1151, Claude, Armstrong County, TX 79019Armstrong BESS, LLC
ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins95% CONFIDENCEOverall confidence: 95%How well the pin's source and references back up its dates.Weighted average of how firmly 3 references support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins at 75% confidence or better
2028-04-17 is the interconnection record’s requested in-service date, not a verified opening or commercial-operation day.
25INR0587 is a 1043.08 MW battery storage interconnection request in Armstrong, TX. The grid operator lists its queue status as SS Completed, FIS Started, No IA. The requested in-service date is 2028-04-17; this is a planning date.
Blytheville I-55 Storage Facility, Interstate 55 Corridor, Blytheville, Mississippi County, AR 72315
ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins95% CONFIDENCEOverall confidence: 95%How well the pin's source and references back up its dates.Weighted average of how firmly 3 references support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins at 75% confidence or better
2028-04-21 is the interconnection record’s requested in-service date, not a verified opening or commercial-operation day.
S1100 is a 200 MW battery storage interconnection request in Mississippi, AR. The grid operator lists its queue status as Active. The requested in-service date is 2028-04-21; this is a planning date.
SCHEDULEDDate confidence: SCHEDULEDGiven as scheduledHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all SCHEDULED pins81% CONFIDENCEOverall confidence: 81%How well the pin's source and references back up its dates.Weighted average of how firmly 5 references, the source included, support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins at 75% confidence or better
The four-and-a-half-year agreements ratified in late 2023 expire on 30 April 2028, a date union leaders set deliberately so that workers could strike on 1 May, International Workers' Day.[1]
The UAW's contracts with General Motors, Ford and Stellantis run out on 30 April 2028 - a date the union chose so members could strike on May Day.
ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins72% CONFIDENCEOverall confidence: 72%How well the pin's source and references back up its dates.Weighted average of how firmly 3 references, the source included, support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins from 50% to 74% confidence
Houston First[1][2] says the fully financed first phase is "on schedule to open in May 2028", a month rather than a day.
A 700,000-square-foot building joined to the George R. Brown Convention Center, holding two exhibition halls, an atrium hall and the largest ballroom in Texas, plus a 100,000-square-foot pedestrian plaza linking it to the Toyota Center. Houston First financed this first phase of its $2 billion convention district transformation with about $1.38 billion of hotel occupancy tax and special revenue bonds.
ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins75% CONFIDENCEOverall confidence: 75%How well the pin's source and references back up its dates.Weighted average of how firmly 7 references, the source included, support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins at 75% confidence or better
EIA’s[2] September 2026 preliminary inventory records a forecast operation month 2028-05. The first day of May 2028 is an estimated month-only display marker, not an exact opening day. The forecast does not prove physical completion and can change in later monthly inventories.
EIA’s September 2026 preliminary inventory identifies AEUG Fleming Solar, LLC, plant 64658, in Fleming County, KY, with 188.5 MW electrical generation nameplate. The listed stage is (U) Under construction, less than or equal to 50 percent complete. Operation is forecast for 2028-05; this is a preliminary survey estimate, not an achieved opening or capacity commitment.
ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins3 years late71% CONFIDENCEOverall confidence: 71%How well the pin's source and references back up its dates.Weighted average of how firmly 5 references, the source included, support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins from 50% to 74% confidence
EIA’s[2] September 2026 preliminary inventory records a forecast operation month 2028-05. The first day of May 2028 is an estimated month-only display marker, not an exact opening day. The forecast does not prove physical completion and can change in later monthly inventories.
EIA’s September 2026 preliminary inventory identifies Accalia Point Solar, LLC, plant 66673, in Cameron County, TX, with 190.5 MW electrical generation nameplate. The listed stage is (P) Planned for installation, but regulatory approvals not initiated. Operation is forecast for 2028-05; this is a preliminary survey estimate, not an achieved opening or capacity commitment.
Oso Negro Clean Energy Storage Facility, West Mesa Industrial & Paseo del Volcan Corridor, Albuquerque, Bernalillo County, NM 87121Oso Negro Energy Storage LLC
ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins95% CONFIDENCEOverall confidence: 95%How well the pin's source and references back up its dates.Weighted average of how firmly 3 references, the source included, support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins at 75% confidence or better
PNM[1] transmission interconnection queue and NMPRC resource adequacy filings schedule the 100 MW Oso Negro battery energy storage project for May 2028 commercial operation.
Development of the Oso Negro Clean Energy Storage Facility in Bernalillo County, New Mexico. Delivering 100 MW / 400 MWh of standalone four-hour lithium-ion battery energy storage along the Public Service Company of New Mexico (PNM) West Mesa 115 kV / 345 kV transmission corridor, the project strengthens grid reliability for the Albuquerque metropolitan load pocket.