Estimated: U.S. Highway 27 near Sargent Road and Wagers Mill Road, south of Newnan, Coweta County, Georgia, United States (approximate: Wagers Mill Road point)
Prologis
The Citizen[1], 10 April 2026: "Coweta County commissioners approved the controversial Project Sail data center Tuesday night in a split 3-2 vote"; Atlanta News First[5], 8 April 2026, confirms the Tuesday-evening vote. No in-service date is published, so the pin is dated to the approval.
Coweta County commissioners approved Atlas Development's rezoning for Project Sail on 7 April 2026 by 3-2, clearing a nine-building, 4.3 million sq ft campus on about 829 acres near Newnan, Georgia that Prologis plans to buy; press describes a 17B USD investment and roughly 900 MW of demand.
$17B