CONFIRMEDDate confidence: CONFIRMEDStated as firmHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all CONFIRMED pins84% CONFIDENCEOverall confidence: 84%How well the pin's source and references back up its dates.Weighted average of how firmly 5 references, the source included, support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins at 75% confidence or betterOracle's[1][2][3][4] release of 27 April 2026: 'Oracle and BorderPlex Digital Assets today announced Project Jupiter will utilize Bloom Energy[5] fuel cells to fully power the AI data center campus'.
Oracle and BorderPlex replaced Project Jupiter's planned gas turbines and diesel generators with up to 2.45 GW of Bloom fuel cells, cutting NOx by about 92% at the Stargate campus in Doña Ana County, New Mexico.