Hinkley Point C Reactor 1 Online
- Hinkley Point C in Somerset is two EPR reactors (2 x 1,630 MWe, 3,260 MWe), owned 76.69% by EDF Energy and 23.31% by China General Nuclear, operated by NNB Generation Company[1]
- Construction began in March 2017 with completion then expected in 2025; delays are attributed to COVID-19, Brexit and budget overruns[1]
- EDF confirmed lower-than-expected productivity in electromechanical installation, so Unit 1 start-up moves to 2030, a year after the previous best case (2029), two years behind the 2027 revised timetable and five behind the original 2025[2][3]
- Cost is £35bn in 2015 prices, about £48bn at today's prices (up £1.4bn), almost double the initial £18bn estimate[1][2][3]
- Progress per EDF results: Unit 1 civil works 94% by concrete volume, 24 primary loop welds finished in January, safety injection pumps installed; Unit 2 dome lifted and reactor pressure vessel delivered; the M&E programme is still behind[2][3]
- Hinkley received £1.6bn from Sizewell C for expertise[2][3]
References 363% CONFIDENCE
The first entry is always the pin's source. Overall confidence is a weighted average of how firmly each reference supports the start and end times used above; a reference counts half as much for every 180 days older than the newest.
- [1]50%en.wikipedia.org/wiki/Hinkley_Point_C_nuclear_power_stationen.wikipedia.org· Posted Sep 11, 2026· Starts Jun 1, 2030 ✓· 52% of score
Given as a target, not a fixed date, per en.wikipedia.org: "…s. As of 2026, Unit 1 of the station is projected to come online in 2030, while the overall project…"
- [2]74%Hinkley Point C M&E productivity hit pushes Unit 1 start-up to 2030industrialisedconstruction.co.uk· Published Mar 2, 2026· 25% of score
Industrialised Construction's headline - "Hinkley Point C M&E productivity hit pushes Unit 1 start-up to 2030" - corroborates the same 2030 target, though the article body was truncated on fetch so only the headline itself could be verified.
- [3]78%M&E delay pushes Hinkley C first reactor start up back a yearconstructionenquirer.com· Published Feb 22, 2026· 24% of score
The Construction Enquirer reports M&E delays pushing "Hinkley C first reactor start up back a year" to 2030, directly matching the pin's stored estimated date and its dateConfidenceReasoning.
Suggest a correction
Something missing or wrong? Say it in your own words: a link that backs this pin up, a different start or end date and why, or a fact it lacks or gets wrong. The AI checks it against this pin's sources, searches for better ones, and adds any page that backs you up. The pin's own sources still count most.