- Start
- Nov 14, 202640% CONFIDENCEfrom the source
J.H. Campbell Coal Plant's Latest Federal Keep-Open Order Ends on 14 November
- DOE issued Order No. 202-26-39 on 14 August 2026 under Federal Power Act section 202(c), directing MISO to keep the coal-fired J.H. Campbell plant available to run from 17 August through 14 November 2026; the plant "was originally slated to shut down on May 31, 2025, 15 years before the end of its scheduled design life"[1]
- It is DOE's sixth order for Campbell, nearly a year and a half beyond the retirement date Michigan regulators approved; the first, of 23 May 2025, was issued days before the planned closure[3][5]
- On 11 September 2026 the US Court of Appeals for the D.C. Circuit unanimously vacated DOE's first order, ruling it an unlawful use of section 202(c); Judge Cornelia Pillard wrote that DOE's position "would empower it to pick its preferred power sources in Michigan"[2][4]
- Consumers Energy told reporters it was reviewing the ruling and did not plan to close the plant immediately; the rulings on the later orders are still pending[4]
- Consumers Energy has reported $295 million of costs for Campbell from May 2025 to 30 June 2026, which it is seeking to recover across the MISO region; retiring the plant was expected to save Michigan ratepayers nearly $600 million[2][5]
References 571% CONFIDENCEOverall confidence: 71%How well the pin's source and references back up its dates.Weighted average of how firmly 5 references, the source included, support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins from 50% to 74% confidence
The first entry is always the pin's source. Overall confidence is a weighted average of how firmly each reference supports the start and end times used above; a reference counts half as much for every 180 days older than the newest.
- [1]40%energy.gov/node/4859847energy.gov· Posted Oct 3, 2026· Starts Nov 14, 2026 ✓· 22% of score
DOE Order No. 202-26-39 "is in effect beginning on August 17, 2026 through November 14, 2026"; Consumers Energy "does not plan to immediately close the plant" after the 11 Sep 2026 appeals ruling (Wisconsin Watch[4]), and DOE has extended its order five times already, so 14 November is when the order lapses, not a guaranteed closure.
- [2]85%Federal Appeals Court Vacates First DOE Order Forcing Operation of J.H. Campbell Coal Plant - Michigan Attorney Generalmichigan.gov· Published Sep 11, 2026· 20% of score
The D.C. Circuit ruling on the first order.[1]
- [3]75%Court strikes down Trump order keeping Michigan coal plant open - FOX 2 Detroitfox2detroit.com· Published Sep 11, 2026· 20% of score
Independent account of the ruling and the plant's original closure plan.[1]
- [4]75%Court ruling spares Wisconsin ratepayers costs of keeping Michigan coal plant open - Wisconsin Watchwisconsinwatch.org· Published Sep 11, 2026· 20% of score
Consumers Energy's[1] response: it does not plan to close the plant immediately.
- [5]85%AG Nessel to Challenge 6th Unlawful DOE Order Forcing Operation of J.H. Campbell Plant - Michigan Attorney Generalmichigan.gov· Published Aug 17, 2026· 18% of score
The sixth order's dates, the costs and the original retirement date.[1]
Suggest a correction
Something missing or wrong? Say it in your own words: a link that backs this pin up, a different start or end date and why, or a fact it lacks or gets wrong. The AI checks it against this pin's sources, searches for better ones, and adds any page that backs you up. The pin's own sources still count most. A picture that shows something else, or shows it badly, is looked at too, and moved down or replaced.