Rowan Percheron Data Center Campus Building 5, Tower Road & East Columbia Avenue Corridor, Boardman, Morrow County, OR 97818Rowan Digital Infrastructure
Rowan Digital Infrastructure Percheron master campus schedule and Umatilla Electric Cooperative transmission planning place Building 5 (84 MW) in 2030 commercial operation.[1]
Rowan Digital Infrastructure development of Building 5 at the Percheron Hyperscale Data Center Campus near Boardman in Morrow County, Oregon. Adding 84 MW of critical IT capacity to complete the five-building 420 MW Percheron campus, Building 5 integrates dedicated 230 kV substation bays and diverse long-haul fiber.
$650M