SCHEDULEDDate confidence: SCHEDULEDGiven as scheduledHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all SCHEDULED pins86% CONFIDENCEOverall confidence: 86%How well the pin's source and references back up its dates.Weighted average of how firmly 5 references, the source included, support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins at 75% confidence or better
A mid-2025 setback added cost and rework but the project team says it is still on schedule. Given as scheduled, per the source[1]: "It is due to be completed in 2030."
Switzerland's second bore under the Gotthard Pass, approved by referendum in 2016 to let the original 1980 tunnel close for renovation without cutting off the A2, is on track to finish by 2030.
Lyndon B. Johnson Space Center, 2101 NASA Parkway, Houston, TX, USANASA
SCHEDULEDDate confidence: SCHEDULEDGiven as scheduledHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all SCHEDULED pins77% CONFIDENCEOverall confidence: 77%How well the pin's source and references back up its dates.Weighted average of how firmly 4 references, the source included, support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins at 75% confidence or better
Given as scheduled, per the source[1]: "NASA[3][4] and its international partners are planning to intentionally deorbit the orbiting laboratory around 2030 or shortly thereafter."
NASA plans to retire the 25-year-old ISS by guiding it into a remote stretch of the South Pacific using a purpose-built SpaceX deorbit vehicle.
Estimated: Switchgrass Industrial Park near U.S. 85, about 8 miles south of Cheyenne, Laramie County, Wyoming (approximate: pin set at Cheyenne city centre; no street address published)Google
ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins64% CONFIDENCEOverall confidence: 64%How well the pin's source and references back up its dates.Weighted average of how firmly 3 references, the source included, support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins from 50% to 74% confidence
Cowboy State Daily[1] (8 July 2026): "Planned completion in 2031"; Cleanview[3] lists Building 2 (464 MW) for 2029, Building 3 (464 MW) for 2030 and Building 4 (678 MW) for 2031.
Google, through its subsidiary Jupiter Star Holdings, is behind Project Tembo (formerly Project Jade), a 2.7 GW (2,700 MW) data-center campus on 716 acres in Switchgrass Industrial Park south of Cheyenne, Wyoming, planned for completion in 2031; no cost has been published.
ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins61% CONFIDENCEOverall confidence: 61%How well the pin's source and references back up its dates.Weighted average of how firmly 5 references, the source included, support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins from 50% to 74% confidence
Given as a target, not a fixed date, per the pin description: "…ructive reentry over the South Pacific. Estimated date.…"
After more than three decades in orbit, the ISS is to be steered into a controlled destructive reentry over the South Pacific. Estimated date.
Green Chapel Road, Jersey Township, Licking County, Ohio 43031, United StatesIntel
DELAYEDDate confidence: DELAYEDThe date has movedHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all DELAYED pins6.5 years late55% CONFIDENCEOverall confidence: 55%How well the pin's source and references back up its dates.Weighted average of how firmly 8 references, the source included, support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins from 50% to 74% confidence
Intel said in February 2025 that the first Ohio module would finish construction in 2030 with operations in 2030-2031 and the second in 2032 (Manufacturing Dive[6], Mar 2025; Spectrum News). January 2031 is the end of that window, used as the estimated start of the full load; month precision.
AEP Ohio built the Green Chapel 138 kV station in Licking County, Ohio, for a chip-fab customer requiring 440 MW at first and up to 1,560 MW at peak; Intel's $28 billion Ohio One fab has slipped to 2030-2031 for the first module, so the substation sits unused and AEP Ohio and Meta have asked to use it temporarily.
Estimated: TeraWulf Muskie Campus Building 7, US Route 23 Industrial Corridor, Catlettsburg, Boyd County, KY 41129TeraWulf
UNVERIFIEDDate confidence: UNVERIFIEDNo wording about the date was foundHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all UNVERIFIED pins40% CONFIDENCEOverall confidence: 40%How well the pin's source and references back up its dates.Weighted average of how firmly 3 references support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins at 49% confidence or below
Separate construction cost, IT power, floor area and an opening date for this building or phase have not been verified. Published campus figures do not establish independent component figures.
Whitley Avenue & 6th Avenue, Corcoran, Kings County, CA 93212Plum Solar LLC
ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins65% CONFIDENCEOverall confidence: 65%How well the pin's source and references back up its dates.Weighted average of how firmly 1 reference, the source included, supports the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins from 50% to 74% confidence
Current online date in CAISO[1] queue 1968, row 204; developer target remains estimated.
CAISO’s current public queue lists PLUM (1968) as active in Kings County, with 1,040 MW photovoltaic and 520 MW storage, limited to 1,000 MW net to grid. Its current online target is March 19, 2031; no $1.2B budget is established.
DELAYEDDate confidence: DELAYEDThe date has movedHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all DELAYED pins2 years late55% CONFIDENCEOverall confidence: 55%How well the pin's source and references back up its dates.Weighted average of how firmly 2 references, the source included, support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins from 50% to 74% confidence
Wikipedia[1] states that "as of July 2024, JR East[2] plans to open the new line in fiscal year 2031"; no month is given, so the pin sits on 1 April 2031, the first day of that Japanese fiscal year.
The new line runs from a station between Haneda's Terminals 1 and 2 through an underwater tunnel to the Tokaido Main Line near Tamachi, tying the airport directly into Tokyo Station and Shin-Kiba. Construction began on 2 June 2023 and the East Yamanote route is costed at about 280 billion yen.
SCHEDULEDDate confidence: SCHEDULEDGiven as scheduledHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all SCHEDULED pins83% CONFIDENCEOverall confidence: 83%How well the pin's source and references back up its dates.Weighted average of how firmly 4 references, the source included, support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins at 75% confidence or better
NASA's[1][2][3][4] eclipse catalogue gives the instant of greatest eclipse as 07:14:46 UT on 2031-05-21 (07:16:04 TD, the two separated by delta-T), from Saros series 138. Eclipse circumstances are computed from orbital mechanics, so the date and time are exact centuries ahead.
Greatest eclipse falls at 07:14:46 UT on 2031-05-21, on a path 152.2 km wide; the annular phase lasts up to 5 minutes 26 seconds, its greatest duration reached further east along the track. The path of annularity crosses Angola, Congo, Zambia, Tanzania, s. India, Malaysia and Indonesia, and a partial eclipse is visible from Africa, southern Asia, the East Indies and Australia.
Estimated: Google Lincoln Campus Building 6, North 56th Street & Interstate 80 Corridor, Lincoln, Lancaster County, NE 68528Google
UNVERIFIEDDate confidence: UNVERIFIEDNo wording about the date was foundHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all UNVERIFIED pins40% CONFIDENCEOverall confidence: 40%How well the pin's source and references back up its dates.Weighted average of how firmly 3 references support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins at 49% confidence or below
Separate construction cost, IT power, floor area and an opening date for this building or phase have not been verified. Published campus figures do not establish independent component figures.
ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins61% CONFIDENCEOverall confidence: 61%How well the pin's source and references back up its dates.Weighted average of how firmly 4 references, the source included, support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins from 50% to 74% confidence
Given as a target, not a fixed date, per en.wikipedia.org[1]: "...is still expected to open in 2031..."
The first fully driverless metro in the United States, reaching Pearl Harbor and downtown Honolulu in its final phase. Estimated date.
ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins63% CONFIDENCEOverall confidence: 63%How well the pin's source and references back up its dates.Weighted average of how firmly 3 references, the source included, support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins from 50% to 74% confidence
Given as a target, not a fixed date, per the pin description: "…unting for matter-antimatter asymmetry. Estimated date.…"
A neutrino beam fired 1,300 km from Fermilab to detectors a mile underground in South Dakota, hunting for matter-antimatter asymmetry. Estimated date.
ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins63% CONFIDENCEOverall confidence: 63%How well the pin's source and references back up its dates.Weighted average of how firmly 2 references, the source included, support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins from 50% to 74% confidence
Proposed completion date in MISO queue entries J4153/J4240 via interconnection.fyi[1][2].
A 250 MW battery project in the MISO queue at the Big Stone South 345 kV substation in Grant County, South Dakota, with a proposed completion of June 2031. Developer and energy (MWh) are not published; a second 250 MW entry (J4240) sits at the same substation.
Estimated: QTS York County Campus DC9, Hands Mill Highway & Campbell Road Corridor, Rock Hill, York County, SC 29745QTS Data Centers (Blackstone)
UNVERIFIEDDate confidence: UNVERIFIEDNo wording about the date was foundHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all UNVERIFIED pins40% CONFIDENCEOverall confidence: 40%How well the pin's source and references back up its dates.Weighted average of how firmly 3 references support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins at 49% confidence or below
Separate construction cost, IT power, floor area and an opening date for this building or phase have not been verified. Published campus figures do not establish independent component figures.
UNVERIFIEDDate confidence: UNVERIFIEDNo wording about the date was foundHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all UNVERIFIED pins40% CONFIDENCEOverall confidence: 40%How well the pin's source and references back up its dates.Weighted average of how firmly 6 references, the source included, support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins at 49% confidence or below
ESA's mission to Ganymede, Callisto and Europa, ending as the first spacecraft to orbit a moon of another planet. Scheduled date.
ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins62% CONFIDENCEOverall confidence: 62%How well the pin's source and references back up its dates.Weighted average of how firmly 3 references, the source included, support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins from 50% to 74% confidence
Given as a target, not a fixed date, per en.wikipedia.org[1]: "…, Plenary Americas, and Webuild) with a projected in-service date of 2031.[37] The contract was valu…"
A 15.6 km automated subway across Toronto with 15 stations, built to relieve the overloaded Line 1. Estimated date.
Estimated: East of State Route 241 and north of Interstate 82, about 11 miles north of Prosser, Benton County, Washington (approximate)BrightNight
ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins65% CONFIDENCEOverall confidence: 65%How well the pin's source and references back up its dates.Weighted average of how firmly 6 references, the source included, support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins from 50% to 74% confidence
Only Cleanview's[4] September 2031 expected date; neither BrightNight nor EFSEC publishes a construction or operating date, and the applicant's 28 October 2025 letter asks for review to continue to 22 December 2026.
BrightNight's Hop Hill project would put up to 500 MW of solar and up to 500 MW of battery storage on about 5,000 acres in Benton County, Washington; Washington's siting council ruled it inconsistent with county zoning on 15 November 2023 and in October 2025 the applicant asked to extend review to 22 December 2026, and no cost has been published.
ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins65% CONFIDENCEOverall confidence: 65%How well the pin's source and references back up its dates.Weighted average of how firmly 1 reference, the source included, supports the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins from 50% to 74% confidence
Broncos FAQ targets the 2031 NFL season. September 1 is an estimated season anchor, not an exact announced opening day; the preferred-site planning process is not construction commencement.[1]
Burnham Yard, a former rail yard less than a mile southeast of Empower Field at Mile High, is the Broncos' preferred site for a privately funded retractable-roof stadium anchoring a mixed-use district of parks, housing, shops and restaurants. The Walton-Penner ownership group is paying for the stadium itself, with Denver and Colorado covering surrounding public improvements.
Estimated: San Joaquin County, California; retained approximate Stockton-area context, not a verified Alta Casa parcel
ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins65% CONFIDENCEOverall confidence: 65%How well the pin's source and references back up its dates.Weighted average of how firmly 1 reference supports the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins from 50% to 74% confidence
October 21, 2031 is CAISO’s[1] proposed completion date, not a confirmed COD.
CAISO lists active queue 1922, Alta Casa Storage, with 515.418 MW battery component capacity and 500 MW maximum export in San Joaquin County. Its current proposed completion date is October 21, 2031, at PG&E’s Tesla 500 kV point of interconnection.
Estimated: East Baseline Road near the Elliott Station substation, Scott Township, Vanderburgh County, IN (approximate; Elliott locality, Evansville)RWE
ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins65% CONFIDENCEOverall confidence: 65%How well the pin's source and references back up its dates.Weighted average of how firmly 4 references, the source included, support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins from 50% to 74% confidence
14News[1] (29 Sep 2026): "The facility is expected to be up and running no later than November 2031". Construction must start by 31 Dec 2029.
RWE Clean Energy Development affiliate Elliot Battery Storage plans a roughly 200 MW, 200M USD battery next to the Elliott Station substation in Scott Township, Vanderburgh County, Indiana; commissioners approved the economic development, decommissioning and road-use agreements on 29 September 2026 and the plant must be running by November 2031.
SCHEDULEDDate confidence: SCHEDULEDGiven as scheduledHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all SCHEDULED pins82% CONFIDENCEOverall confidence: 82%How well the pin's source and references back up its dates.Weighted average of how firmly 3 references, the source included, support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins at 75% confidence or better
NASA's[1][2][3] eclipse catalogue gives the instant of greatest eclipse as 21:06:12 UT on 2031-11-14 (21:07:30 TD, the two separated by delta-T), from Saros series 143. Eclipse circumstances are computed from orbital mechanics, so the date and time are exact centuries ahead.
The Moon's shadow touches down at 21:06:12 UT on 2031-11-14, and the hybrid phase lasts up to 1 minute 8 seconds along a path 38.3 km wide crossing the Pacific and Panama. A partial eclipse is visible from the Pacific, southern the United States, Central America and northwestern South America.
Estimated: Sherman County, Oregon, USA (approximate EIA reporting point)Cedar Island Solar LLC
ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins65% CONFIDENCEOverall confidence: 65%How well the pin's source and references back up its dates.Weighted average of how firmly 1 reference supports the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins from 50% to 74% confidence
EIA[1]-860M August 2026 planned-operation month December 2031; month placeholder, approvals pending.
EIA’s August 2026 planned-generator inventory lists Cedar Island Solar LLC, plant 66011/PV 1, at 800 MW in Sherman County, with December 2031 planned operation and regulatory approvals pending, not under construction. The old$950 M budget and 2029 date are unsupported.
Pierce Clean Solar Energy Center, US Highway 81 & State Highway 13 Corridor, Pierce, Pierce County, NE 68767
ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins65% CONFIDENCEOverall confidence: 65%How well the pin's source and references back up its dates.Weighted average of how firmly 3 references support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins from 50% to 74% confidence
2031-12-01 is the interconnection record’s requested in-service date, not a verified opening or commercial-operation day.
GEN-2018-131 is a 221.4 MW photovoltaic generation interconnection request in Pierce, NE. The grid operator lists its queue status as IA FULLY EXECUTED/ON SCHEDULE. The requested in-service date is 2031-12-01; this is a planning date.
ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins51% CONFIDENCEOverall confidence: 51%How well the pin's source and references back up its dates.Weighted average of how firmly 3 references, the source included, support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins from 50% to 74% confidence
Estimated: December 2031 is an inherited planning marker, not a verified Eolus[1] opening commitment. The current developer page gives no completion schedule; the 2023 special-use request was withdrawn. A fresh primary interconnection record is needed to reconcile the precise date and the overlapping Hoodini queue pin.
Eolus lists Hoodini in planning with 450 MW of solar and a separate 450 MW storage component in Dateland, Arizona. A current budget and committed opening date are unpublished.
Roma Clean Energy Storage Center, Vernon Boulevard & Astoria Waterfront Transmission Corridor, Long Island City, Queens County, NY 11106Roma Storage LLC
ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins65% CONFIDENCEOverall confidence: 65%How well the pin's source and references back up its dates.Weighted average of how firmly 3 references support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins from 50% to 74% confidence
2031-12 is the requested commercial-operation month in NYISO[1][3]. Day 01 is only a month-precision anchor, not an announced commissioning day.
C26-0002 is a 300 MW battery storage interconnection request in Queens, NY. The grid operator lists its queue status as Active interconnection request. The requested in-service date is 2031-12-01; this is a planning date.
ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins50% CONFIDENCEOverall confidence: 50%How well the pin's source and references back up its dates.Weighted average of how firmly 5 references support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins from 50% to 74% confidence
2031-12 is the preliminary planned operation month in EIA's[3] September 2026 survey (approvals pending). Day 01 is a month-precision anchor, not an announced opening day.
EIA's September 2026 preliminary inventory lists 800 MW of photovoltaic nameplate capacity at Cedar Island Solar LLC in Sherman County, Oregon (reference point 45.2337, -120.8985 reported to EIA). Reported planned operation month: December 2031, with regulatory approvals pending. Cleanview lists Enlight Renewable Energy's pipeline as including Cedar Island Solar LLC, 800 MW, Oregon.
Renforth Drive at Eglinton Avenue West, Etobicoke, Toronto, Ontario, CanadaMetrolinx
DELAYEDDate confidence: DELAYEDThe date has movedHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all DELAYED pins8 years late55% CONFIDENCEOverall confidence: 55%How well the pin's source and references back up its dates.Weighted average of how firmly 2 references, the source included, support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins from 50% to 74% confidence
The article says only that "The extension is expected to open in 2031", a year rather than a fixed day, so the pin sits on the last day of that year.[1]
The 9.2-kilometre westward extension of Line 5 Eglinton adds seven stations - four underground, two elevated and one in an open trench - ending at a trenched terminal at Renforth beside the eastern end of the Mississauga Transitway. Construction was estimated in 2026 at CA$3.97 billion, up from CA$2.47 billion a decade earlier.
Estimated: Approximate location in the reported project area; exact parcel pending
ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins65% CONFIDENCEOverall confidence: 65%How well the pin's source and references back up its dates.Weighted average of how firmly 1 reference supports the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins from 50% to 74% confidence
December 31, 2031 is the current queue’s requested date, not a guaranteed commissioning date; the prior December 2028 estimate is replaced.
CAISO’s current public queue lists active HOODINI request 1663 in Yuma County with 459.54 MW photovoltaic and 450 MW storage, limited to 450 MW net export, at SDG&E’s Hoodoo Wash 500 kV switchyard. Current requested date is December 31, 2031.
DOE Paducah Site, McCracken County, Kentucky, United StatesBrookfield
ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins65% CONFIDENCEOverall confidence: 65%How well the pin's source and references back up its dates.Weighted average of how firmly 4 references, the source included, support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins from 50% to 74% confidence
DCD, 29 July 2026: "at full build-out, the campus could support up to 1.8GW of utility capacity and more than 1.2GW of compute capacity by 2032"; POWER and DOE-based reports say construction is expected to finish in 2031. No month is given.[1]
Brookfield will lease land at the DOE Paducah Site in McCracken County, Kentucky for a campus of up to 1,800 MW of utility capacity (more than 1,200 MW of compute) with NextEra building up to 4.6 GW of dedicated generation and storage; the coalition cites 100B USD of private investment and full build-out in 2032.
Estimated: Google Lincoln Campus Building 7, North 56th Street & Interstate 80 Corridor, Lincoln, Lancaster County, NE 68528Google
UNVERIFIEDDate confidence: UNVERIFIEDNo wording about the date was foundHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all UNVERIFIED pins40% CONFIDENCEOverall confidence: 40%How well the pin's source and references back up its dates.Weighted average of how firmly 3 references support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins at 49% confidence or below
Separate construction cost, IT power, floor area and an opening date for this building or phase have not been verified. Published campus figures do not establish independent component figures.