DELAYEDDate confidence: DELAYEDThe date has movedHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all DELAYED pins6 months late55% CONFIDENCEOverall confidence: 55%How well the pin's source and references back up its dates.Weighted average of how firmly 3 references, the source included, support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins from 50% to 74% confidence
LTA's[1] March 2026 rail factsheet says "Stage 1 of the JRL will open around mid-2028, instead of the initial end-2027 timeline", so the day here stands for mid-2028.
The first stage of Singapore's fully elevated, driverless Jurong Region Line opens, serving Tengah and the western estates around Choa Chu Kang. LTA pushed the opening back by about six months after viaduct construction over the Pan-Island Expressway could only be carried out during overnight road closures, and will run interim shuttle buses from end-2027 until the line opens.
ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins65% CONFIDENCEOverall confidence: 65%How well the pin's source and references back up its dates.Weighted average of how firmly 2 references, the source included, support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins from 50% to 74% confidence
Unverified legacy June 2028 date. Historical concept has no verified service schedule and current local reporting says no active city proposals.[1]
June 2025 reporting lists Cielo’s Chisago concept at 300 MW on 157 acres. June 2026 local reporting says the city had no current proposals and an earlier unnamed project was dropped over grid limits; a direct identity match still needs city records.
ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins65% CONFIDENCEOverall confidence: 65%How well the pin's source and references back up its dates.Weighted average of how firmly 4 references, the source included, support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins from 50% to 74% confidence
Operator schedules completion in June 2028; June 30 is an estimated month-end anchor, not an announced exact handover date.[1]
Aena is doubling the boarding and arrivals area to 105,000 square metres and replacing the airport's 12 airbridges with 19, so that 70 per cent of boardings are direct to the aircraft. A new 215,000-square-metre apron takes commercial aircraft stands from 30 to 37 and lifts capacity to 29.5 million passengers a year; work began in 2024.
Elk Clean Solar Complex, K-99 Highway Corridor, Howard, Elk County, KS 67349
ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins65% CONFIDENCEOverall confidence: 65%How well the pin's source and references back up its dates.Weighted average of how firmly 3 references support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins from 50% to 74% confidence
2028-06-30 is the interconnection record’s requested in-service date, not a verified opening or commercial-operation day.
GEN-2024-125 is a 400 MW photovoltaic generation interconnection request in Elk, KS. The grid operator lists its queue status as DISIS STAGE. The requested in-service date is 2028-06-30; this is a planning date.
ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins65% CONFIDENCEOverall confidence: 65%How well the pin's source and references back up its dates.Weighted average of how firmly 2 references, the source included, support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins from 50% to 74% confidence
Unverified legacy June 2028 placeholder; June 2026 reporting describes a stalled utility inquiry with no formal application.[1]
FOX 13’s June 2026 reporting says Haines City lacks water capacity for Cielo’s proposed data center and had no formal applications. Historical developer-site reporting gives 300 MW on 74 acres; the $1.8B budget and 2028 opening were not verified.
Hazleton Clean Storage Site, 130th Street Corridor, Hazleton, Buchanan County, IA 50641
ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins65% CONFIDENCEOverall confidence: 65%How well the pin's source and references back up its dates.Weighted average of how firmly 3 references support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins from 50% to 74% confidence
2028-06-30 is the interconnection record’s requested in-service date, not a verified opening or commercial-operation day.
J3780 is a 205 MW battery storage interconnection request in Buchanan, IA. The grid operator lists its queue status as Active. The requested in-service date is 2028-06-30; this is a planning date.
ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins65% CONFIDENCEOverall confidence: 65%How well the pin's source and references back up its dates.Weighted average of how firmly 2 references, the source included, support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins from 50% to 74% confidence
Rubin's early-science plan gives the LSST[1] start as 2026-06-29 and says processing one year of data "is estimated to require approximately one year", which "implies an expected DR1 delivery approximately two years after the effective start" - while warning the boundaries are set by "survey performance and scientific readiness rather than a fixed calendar date".
Rubin's Data Release 1, built from the first year of the Legacy Survey of Space and Time, is expected about two years after the survey began on 29 June 2026.
FM 1057 & County Road 12, Hereford, Deaf Smith County, TX 79045Intersect Power
ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins65% CONFIDENCEOverall confidence: 65%How well the pin's source and references back up its dates.Weighted average of how firmly 1 reference, the source included, supports the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins from 50% to 74% confidence
ERCOT[1] September 2026 GIS report row 1557 projected COD; estimated until actual commissioning evidence.
ERCOT’s September 2026 GIS report lists Aurelius Solar (29INR0003), IP Roman LLC, at 1,124.24 MW in Deaf Smith County, with an executed interconnection agreement and June 30, 2028 projected COD. No $1.3B budget is established.
Bloomberg L.P., 731 Lexington Avenue, New York, NYBloomberg
ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins65% CONFIDENCEOverall confidence: 65%How well the pin's source and references back up its dates.Weighted average of how firmly 3 references, the source included, support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins from 50% to 74% confidence
Estimated: a "by when" market with no scheduled event behind it. The largest step between consecutive strikes (taking the highest quote seen so far where a later strike is quoted lower) is Jul 1, 2028 (24%) to Jan 1, 2029 (35%), so the window opens on Jul 1, 2028. Quotes are bid/ask midpoints read on 27 October 2026. Estimated contract-count-times-last-price volume across active strikes is about US$2,311 (10,128 contracts); this is not reported cash turnover.[1]
Kalshi
On 27 October 2026 Kalshi put an official Bloomberg IPO confirmation at 3.5% before Jan 1, 2027, rising to 50% before Jan 1, 2030. The largest step in the ladder runs from Jul 1, 2028 to Jan 1, 2029 (24% to 35%), so that window is the market's most likely stretch; it is a bet on timing, not a listing date.
ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins50% CONFIDENCEOverall confidence: 50%How well the pin's source and references back up its dates.Weighted average of how firmly 1 reference, the source included, supports the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins from 50% to 74% confidence
ClinicalTrials.gov[1] lists 2028-07-05 as the estimated primary completion date; a sponsor's estimate, and trials of this size routinely slip.
AstraZeneca's phase 3 trial of Elecoglipron in type 2 diabetes mellitus reaches primary completion, the point at which the last participant's primary outcome is measured. The trial enrolled 2,000 participants. The purpose of this study is to evaluate the efficacy, safety, and tolerability of elecoglipron and dapagliflozin in combination, compared with elecoglipron alone and dapagliflozin alone, in adults with type 2 diabetes mellitus (T2DM) inadequately managed with lifestyle management alone or treated with other background glucose-lowering medication.
SCHEDULEDDate confidence: SCHEDULEDGiven as scheduledHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all SCHEDULED pins78% CONFIDENCEOverall confidence: 78%How well the pin's source and references back up its dates.Weighted average of how firmly 3 references, the source included, support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins at 75% confidence or better
The Games have a fixed published date: the 2028 Summer Olympics open on 14 July 2028 at the Los Angeles Memorial Coliseum.[1]
Los Angeles hosts its third Games after 1932 and 1984, using almost entirely existing venues.
Los Angeles Memorial Coliseum, Los Angeles, California, USALA28
SCHEDULEDDate confidence: SCHEDULEDGiven as scheduledHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all SCHEDULED pins77% CONFIDENCEOverall confidence: 77%How well the pin's source and references back up its dates.Weighted average of how firmly 3 references, the source included, support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins at 75% confidence or better
Given as scheduled, per the source[1]: the Games are set for "the Summer of 2028," following the IOC's 2017 award to Los Angeles.
Los Angeles is preparing to host the 2028 Summer Olympics with zero new venues and a 'no-car' transit plan, a bold bet for a city not known for its public transport.
Estimated: Freestone County, Texas; approximate shared Amerada solar EIA reporting context, not a surveyed battery parcelAmerada Solar, LLC
ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins65% CONFIDENCEOverall confidence: 65%How well the pin's source and references back up its dates.Weighted average of how firmly 2 references support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins from 50% to 74% confidence
ERCOT[1] battery projected COD; separate EIA[2] solar schedule is not substituted.
ERCOT identifies Amerada Storage as 26INR0084, Amerada Solar LLC, 150.78 MW in Freestone County, targeting July 21, 2028. Screening is complete and full study started without an IA; this is a development request.
UNVERIFIEDDate confidence: UNVERIFIEDNo wording about the date was foundHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all UNVERIFIED pins40% CONFIDENCEOverall confidence: 40%How well the pin's source and references back up its dates.Weighted average of how firmly 3 references, the source included, support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins at 49% confidence or below
Totality passes directly over central Sydney for nearly four minutes, the first there since 1857.
ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins50% CONFIDENCEOverall confidence: 50%How well the pin's source and references back up its dates.Weighted average of how firmly 1 reference, the source included, supports the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins from 50% to 74% confidence
ClinicalTrials.gov[1] lists 2028-07-24 as the estimated primary completion date; a sponsor's estimate, and trials of this size routinely slip.
Roche's phase 3 trial of Enicepatide in obesity or overweight reaches primary completion, the point at which the last participant's primary outcome is measured. The trial enrolled 2,000 participants. The purpose of this study is to assess the efficacy and safety of enicepatide, a dual glucagon like peptide-1 (GLP-1)/glucose-dependent insulinotropic polypeptide (GIP) receptor agonist (RA), at multiple doses compared with placebo for weight management in participants without Type 2 diabetes mellitus (T2DM) who have obesity or overweight with at least one weight-related comorbidity.
SCHEDULEDDate confidence: SCHEDULEDGiven as scheduledHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all SCHEDULED pins81% CONFIDENCEOverall confidence: 81%How well the pin's source and references back up its dates.Weighted average of how firmly 3 references, the source included, support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins at 75% confidence or better
The contract agreed in 2023 runs to 31 July 2028; FreightWaves[1] reports Teamsters president Sean O'Brien saying the union is ready to strike when it expires.
The five-year UPS-Teamsters agreement covering some 340,000 workers expires on 31 July 2028, and the union's president has already said a strike is coming.
Near Wilson, Mississippi County, Arkansas, USA (EIA reported project point)Cypress Creek Energy
ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins65% CONFIDENCEOverall confidence: 65%How well the pin's source and references back up its dates.Weighted average of how firmly 2 references support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins from 50% to 74% confidence
EIA[2] plant 70397 August 2028 target; month precision. Operator all-phase 2029 target differs from EIA Phase 3 July 2030.
EIA’s August 2026 inventory lists Steel River Solar Phase 1 (plant 70397) with a 250 MW battery and 500 MW solar, planned for August 2028. This is a phase of Cypress Creek’s broader hybrid development, rather than a proven standalone $220M/1,000 MWh battery.
Hampton-Prairie Island Solar Center, US Highway 52 Corridor, Cannon Falls, Goodhue County, MN 55009
ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins65% CONFIDENCEOverall confidence: 65%How well the pin's source and references back up its dates.Weighted average of how firmly 3 references support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins from 50% to 74% confidence
2028-08-01 is the interconnection record’s requested in-service date, not a verified opening or commercial-operation day.
J3399 is a 300 MW photovoltaic generation interconnection request in Goodhue, MN. The grid operator lists its queue status as Active. The requested in-service date is 2028-08-01; this is a planning date.
Steel River EIA plant 70397 reporting point, Mississippi County, Arkansas; shared program reporting context, not a surveyed Phase 1 footprintCypress Creek Energy
ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins65% CONFIDENCEOverall confidence: 65%How well the pin's source and references back up its dates.Weighted average of how firmly 4 references support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins from 50% to 74% confidence
August 2028 is EIA[1] planned month; day 1 is placeholder, not guaranteed COD. Operator2029 whole-program target and EIA Phase 3 July 2030 remain unresolved.
EIA August 2026 lists Cypress Creek’s Steel River Solar Phase 1, plant 70397, with 500 MW solar SRSP1 and separate 250 MW battery SRSB1, under construction at most 50% complete and planned for August 2028. Operator announced groundbreaking for the first two phases in July 2026.
Okolona Clean Solar Center, State Highway 41 & US Highway 45W Corridor, Okolona, Chickasaw County, MS 38860NextEra Energy Resources
ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins65% CONFIDENCEOverall confidence: 65%How well the pin's source and references back up its dates.Weighted average of how firmly 4 references support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins from 50% to 74% confidence
The cited project source establishes 2028-08. Preserve the stated precision; a year, month or quarter anchor is not an announced exact opening day.
NextEra describes Okolona Solar as a proposed up-to-145 MW project in Chickasaw County, Mississippi, targeting operations as early as August 2028 subject to permits and approvals.
Estimated: Clay County, Minnesota; approximate county context, exact J3762 parcel pending
ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins65% CONFIDENCEOverall confidence: 65%How well the pin's source and references back up its dates.Weighted average of how firmly 1 reference supports the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins from 50% to 74% confidence
August 1, 2028 is MISO’s requested inService date, not confirmed COD.
MISO lists J3762 as a 430 MW solar request at Alexandria–Bison 345 kV in Clay County, Minnesota. The active Phase 2 request carries an August 1, 2028 in-service target; Great River Energy is the transmission owner, not verified developer.
Blue Spruce Clean Energy Storage Center, Locust Avenue & East 138th Street Waterfront Corridor, Bronx, Bronx County, NY 10454Blue Spruce Storage LLC
ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins65% CONFIDENCEOverall confidence: 65%How well the pin's source and references back up its dates.Weighted average of how firmly 3 references support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins from 50% to 74% confidence
2028-08 is the requested commercial-operation month in NYISO[1][3]. Day 01 is only a month-precision anchor, not an announced commissioning day.
C24-005 is a 300 MW battery storage interconnection request in Bronx, NY. The grid operator lists its queue status as Active interconnection request. The requested in-service date is 2028-08-01; this is a planning date.
ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins50% CONFIDENCEOverall confidence: 50%How well the pin's source and references back up its dates.Weighted average of how firmly 1 reference, the source included, supports the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins from 50% to 74% confidence
ClinicalTrials.gov[1] lists 2028-08-11 as the estimated primary completion date; a sponsor's estimate, and trials of this size routinely slip.
AstraZeneca's phase 3 trial of AZD6234 in obesity or overweight reaches primary completion, the point at which the last participant's primary outcome is measured. The trial enrolled 2,500 participants. The study will evaluate how well AZD6234 works and how safe it is in adults with excess weight or obesity.
SCHEDULEDDate confidence: SCHEDULEDGiven as scheduledHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all SCHEDULED pins85% CONFIDENCEOverall confidence: 85%How well the pin's source and references back up its dates.Weighted average of how firmly 5 references, the source included, support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins at 75% confidence or better
Wikipedia's[1][3] article dates it "from August 15 to August 27, 2028".
LA28’s first Paralympic Games open August 15, 2028 at SoFi Stadium in Inglewood and run through August 27. The Coliseum hosts the closing ceremony, so the opening pin is mapped to SoFi.
ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins50% CONFIDENCEOverall confidence: 50%How well the pin's source and references back up its dates.Weighted average of how firmly 1 reference, the source included, supports the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins from 50% to 74% confidence
ClinicalTrials.gov[1] lists 2028-08-30 as the estimated primary completion date; a sponsor's estimate, and trials of this size routinely slip.
Boehringer Ingelheim's phase 3 trial of BI 690517 in kidney disease, chronic reaches primary completion, the point at which the last participant's primary outcome is measured. The trial enrolled 11,000 participants. This study is open to adults with chronic kidney disease at risk of progression. People with and without type 2 diabetes can take part in this study. The study is open to people who take other medicines called angiotensin converting enzyme inhibitors (ACEi) or angiotensin receptor blockers (ARB). People who already take empagliflozin or any other sodium-glucose cotransporter-2 inhibitor (SGLT2i) can also join. The study is also open to people who currently do not take any of these treatments. The purpose of this study is to find out whether a medicine called BI 690517 helps people with chronic kidney disease when taken in combination with a study medicine called empagliflozin. Worsening of kidney function increases the risk for kidney failure, cardiovascular disease, and heart failure hospitalisation.
10, Piccadilly, St. James's, East Marylebone, Mayfair, City of Westminster, Greater London, England, W1J 0DD, United KingdomTime Out Group
SCHEDULEDDate confidence: SCHEDULEDGiven as scheduledHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all SCHEDULED pins73% CONFIDENCEOverall confidence: 73%How well the pin's source and references back up its dates.Weighted average of how firmly 3 references, the source included, support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins from 50% to 74% confidence
Time Out's[1][3] own announcement of 6 August 2026 says the market will open "in the summer of 2028" at 10 Piccadilly. A season is a period, so the pin takes its last day; northern-hemisphere summer closes at the end of August, giving 31 August 2028. It will move when a day is published - this is two years out and the building is still in development.
Time Out brings its market home to the city where the magazine started in 1968: 26,400 square feet over three floors at 10 Piccadilly, on a long-term partnership with The Crown Estate, as the flagship of the whole portfolio.
2146 Red House Road, Richmond, Kentucky, United StatesAcciona Energia
ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins65% CONFIDENCEOverall confidence: 65%How well the pin's source and references back up its dates.Weighted average of how firmly 5 references, the source included, support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins from 50% to 74% confidence
Only the EIA[2]-860M proposed operating date of 1 September 2028 (as listed by Cleanview[4]) is available; Global Energy Monitor shows 2027, and no Acciona or Siting Board document gives a construction or operation date.
Acciona's AEUG Madison Solar would be a 100 MWac merchant solar farm on about 1,100 acres near Richmond, Madison County, Kentucky; it holds a conditional siting certificate from 2021 but no construction start or cost has been published.
Estimated: Wexford County, Michigan; approximate county context, exact J3723 parcel pending
ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins65% CONFIDENCEOverall confidence: 65%How well the pin's source and references back up its dates.Weighted average of how firmly 1 reference supports the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins from 50% to 74% confidence
September 1, 2028 is the queue inService target, not confirmed COD.
MISO lists active J3723 as a 300 MW solar request in Wexford County, Michigan, at Keystone–Ludington 345 kV. The Phase 2 request has a September 1, 2028 in-service target; METC is transmission owner.
ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins65% CONFIDENCEOverall confidence: 65%How well the pin's source and references back up its dates.Weighted average of how firmly 1 reference supports the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins from 50% to 74% confidence
September 1, 2028 is the queue’s requested inService target, not confirmed COD.
MISO lists J3454 as a 300 MW solar request in Morehouse Parish, Louisiana, at Baxter Wilson SES–Perryville 500 kV. The active Phase 2 request carries a September 1, 2028 in-service target.
Estimated: Google West Memphis Hyperscale Campus Building 4, Service Road Corridor, West Memphis, AR 72301Google LLC
UNVERIFIEDDate confidence: UNVERIFIEDNo wording about the date was foundHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all UNVERIFIED pins40% CONFIDENCEOverall confidence: 40%How well the pin's source and references back up its dates.Weighted average of how firmly 3 references support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins at 49% confidence or below
Separate construction cost, IT power, floor area and an opening date for this building or phase have not been verified. Published campus figures do not establish independent component figures.