Nouvelle Route du Littoral, La Grande Chaloupe, Saint-Denis, La Réunion, France
ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins78% CONFIDENCEOverall confidence: 78%How well the pin's source and references back up its dates.Weighted average of how firmly 6 references, the source included, support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins at 75% confidence or better
Retains June 30, 2030 as an estimated mid-year anchor for full-road commissioning. May 2026 site reporting confirms a 2030 completion horizon; this is not an exact announced opening day or the 2027 interchange completion.[1]
The final offshore-viaduct section of Réunion's storm-battered coastal highway replacement, plagued by quarry bans and redesigns, is now due to fully open by mid-2030.
State Highway 18 & Farm to Market Road 1450, Fort Stockton, Pecos County, TX 79735S&S Renewables LLC
ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins95% CONFIDENCEOverall confidence: 95%How well the pin's source and references back up its dates.Weighted average of how firmly 1 reference supports the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins at 75% confidence or better
ERCOT[1] September 2026 GIS row1745 projected COD; no IA, estimated.
ERCOT’s September 2026 report lists Gravitas I Solar (30INR0083), S&S Renewables LLC, in Pecos County at 1,124.75 MW, with projected COD June 30, 2030 and no interconnection agreement. The prior $1.3B cost is unsupported.
US Highway 285 & County Road 101, Fort Stockton, Pecos County, TX 79735S&S Renewables LLC
ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins95% CONFIDENCEOverall confidence: 95%How well the pin's source and references back up its dates.Weighted average of how firmly 1 reference supports the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins at 75% confidence or better
ERCOT’s September 2026 report identifies Permian I Solar (31INR0018), S&S Renewables LLC, at 1,125.73 MW in Pecos County. The entry has no interconnection agreement and projects June 30, 2030 COD; the former $1.3B budget is removed.
Rork-Sellers Road Storage Facility, US Highway 90 Corridor, Lafayette, Lafayette Parish, LA 70501
ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins95% CONFIDENCEOverall confidence: 95%How well the pin's source and references back up its dates.Weighted average of how firmly 3 references support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins at 75% confidence or better
2030-06-30 is the interconnection record’s requested in-service date, not a verified opening or commercial-operation day.
J4098 is a 300 MW battery storage interconnection request in Lafayette, LA. The grid operator lists its queue status as Active. The requested in-service date is 2030-06-30; this is a planning date.
Pere Marquette Energy Storage Facility, Pere Marquette Highway, Ludington, Mason County, MI 49431
ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins95% CONFIDENCEOverall confidence: 95%How well the pin's source and references back up its dates.Weighted average of how firmly 3 references support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins at 75% confidence or better
2030-06-30 is the interconnection record’s requested in-service date, not a verified opening or commercial-operation day.
J4093 is a 400 MW battery storage interconnection request in Mason, MI. The grid operator lists its queue status as Active. The requested in-service date is 2030-06-30; this is a planning date.
Wabaco Energy Storage Facility, US Highway 61 Corridor, Wabasha, Wabasha County, MN 55981
ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins95% CONFIDENCEOverall confidence: 95%How well the pin's source and references back up its dates.Weighted average of how firmly 3 references support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins at 75% confidence or better
2030-06-30 is the interconnection record’s requested in-service date, not a verified opening or commercial-operation day.
J3848 is a 250 MW battery storage interconnection request in Wabasha, MN. The grid operator lists its queue status as Active. The requested in-service date is 2030-06-30; this is a planning date.
ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins95% CONFIDENCEOverall confidence: 95%How well the pin's source and references back up its dates.Weighted average of how firmly 1 reference supports the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins at 75% confidence or better
June 30, 2030 is MISO’s requested inService date, not confirmed COD.
MISO lists J3840 as an active 300 MW battery request at Wells in St. Landry Parish, Louisiana. The DPP-2025 Phase 1 request carries a June 30, 2030 in-service target and lists Cleco as transmission owner.
Finney County Solar Project, US Route 50 Corridor, Garden City, Finney County, KS 67846
ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins95% CONFIDENCEOverall confidence: 95%How well the pin's source and references back up its dates.Weighted average of how firmly 3 references support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins at 75% confidence or better
2030-06-30 is the interconnection record’s requested in-service date, not a verified opening or commercial-operation day.
GEN-2023-015 is a 330 MW photovoltaic generation interconnection request in Finney County, KS. The grid operator lists its queue status as FACILITY STUDY STAGE. The requested in-service date is 2030-06-30; this is a planning date.
California Air Resources Board, 1001, I Street, Downtown, Sacramento, Sacramento County, California, 95814, United StatesCalRecycle
SCHEDULEDDate confidence: SCHEDULEDGiven as scheduledHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all SCHEDULED pins81% CONFIDENCEOverall confidence: 81%How well the pin's source and references back up its dates.Weighted average of how firmly 3 references, the source included, support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins at 75% confidence or better
SB 707's own statutory timeline fixes July 1, 2030 as the date by which the Producer Responsibility Organization 'must have a plan that has been approved by CalRecycle' running in full, per the bill text and implementation trackers built from it.[1]
SB 707, California's landmark textile extended-producer-responsibility law, requires its Producer Responsibility Organization to have a fully approved collection-and-recycling plan running statewide by July 1, 2030.
Steel River Phase 3 EIA plant 70399 shared reporting point, Mississippi County, Arkansas; not independently surveyed battery parcelCypress Creek Renewables LLC
ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins95% CONFIDENCEOverall confidence: 95%How well the pin's source and references back up its dates.Weighted average of how firmly 4 references support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins at 75% confidence or better
EIA[2] planned month July 2030; day 1 is a month placeholder. Operator expects all phases by 2029, an unresolved discrepancy for Phase 3.
EIA’s September 2026 inventory identifies Steel River Solar Phase 3, plant 70399, with 250 MW battery SRSB3 and a separate 500 MW solar generator. It reports construction no more than 50% complete and July 2030 planned operation.
Steel River EIA plant 70399 reporting point, Mississippi County, Arkansas; shared program reporting context, not a surveyed Phase 3 footprintCypress Creek Energy
ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins95% CONFIDENCEOverall confidence: 95%How well the pin's source and references back up its dates.Weighted average of how firmly 4 references support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins at 75% confidence or better
EIA[1] July 2030 planned month; day 1 is a placeholder, not guaranteed COD. Operator all-phase 2029 target conflicts and remains explicit.
EIA August 2026 lists Cypress Creek’s Steel River Solar Phase 3, plant 70399, with 500 MW SRSP3 solar and separate 250 MW SRSB3 battery, under construction at most 50% complete and planned for July 2030. Operator whole-program timing instead targets all three phases by 2029.
Lighthouse Energy Storage Facility, Lake Shore Drive & Dunkirk 230 kV Substation Corridor, Dunkirk, Chautauqua County, NY 14048Lighthouse Battery, LLC
ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins95% CONFIDENCEOverall confidence: 95%How well the pin's source and references back up its dates.Weighted average of how firmly 3 references support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins at 75% confidence or better
2030-07 is the requested commercial-operation month in NYISO[1][3]. Day 01 is only a month-precision anchor, not an announced commissioning day.
C24-074 is a 250 MW battery storage interconnection request in Chautauqua, NY. The grid operator lists its queue status as Active interconnection request. The requested in-service date is 2030-07-01; this is a planning date.
Estimated: TeraWulf Muskie Campus Building 5, US Route 23 Industrial Corridor, Catlettsburg, Boyd County, KY 41129TeraWulf
UNVERIFIEDDate confidence: UNVERIFIEDNo wording about the date was foundHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all UNVERIFIED pins72% CONFIDENCEOverall confidence: 72%How well the pin's source and references back up its dates.Weighted average of how firmly 3 references support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins from 50% to 74% confidence
Separate construction cost, IT power, floor area and an opening date for this building or phase have not been verified. Published campus figures do not establish independent component figures.
ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins75% CONFIDENCEOverall confidence: 75%How well the pin's source and references back up its dates.Weighted average of how firmly 4 references, the source included, support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins at 75% confidence or better
WECC and PacifiCorp generation interconnection queue schedules target August 2030 commercial operation.[1]
Avantus is developing the 300 MWac Gale 1 Solar project on state and private lands in Millard County near Delta, Utah. Taking advantage of the high-insolation Sevier River basin and transmission corridors anchored by the Intermountain Power Project, the project includes optional co-located battery storage to supply clean peak generation to the regional Western grid.
Estimated: Kent County, Texas; retained approximate county/project-area context pending a sourced parcelOrigis Development, LLC
ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins95% CONFIDENCEOverall confidence: 95%How well the pin's source and references back up its dates.Weighted average of how firmly 1 reference supports the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins at 75% confidence or better
September 1, 2030 is ERCOT[1] projected COD, not a confirmed service date.
ERCOT September 2026 GIS identifies Buzzer Butte 2 Solar request 30INR0164 in Kent County: 242.8 MW, Origis Development LLC, screening and full study started with no IA, targeting September 1, 2030.
Willard Clean Energy Storage Facility, Reynolds Road & Alps 345 kV Transmission Corridor, North Greenbush, Rensselaer County, NY 12144Emeren US, LLC
ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins95% CONFIDENCEOverall confidence: 95%How well the pin's source and references back up its dates.Weighted average of how firmly 3 references support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins at 75% confidence or better
2030-09 is the requested commercial-operation month in NYISO[1][3]. Day 01 is only a month-precision anchor, not an announced commissioning day.
C24-148 is a 300 MW battery storage interconnection request in Rensselaer, NY. The grid operator lists its queue status as Active interconnection request. The requested in-service date is 2030-09-01; this is a planning date.
Estimated: Jasper County, Indiana; approximate county context, J3931 has no published parcel here
ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins95% CONFIDENCEOverall confidence: 95%How well the pin's source and references back up its dates.Weighted average of how firmly 1 reference supports the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins at 75% confidence or better
September 30, 2030 is the request’s inService date, not confirmed commissioning.
MISO’s active J3931 request is a 500 MW photovoltaic project in Jasper County, Indiana, targeting September 30, 2030. It is in DPP-2025 Phase 1 with POI recorded only as Other_; NIPSCO is listed as transmission owner.
Cedar Mountain Solar Facility, State Highway 67 Corridor, Redwood Falls, Redwood County, MN 56283
ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins95% CONFIDENCEOverall confidence: 95%How well the pin's source and references back up its dates.Weighted average of how firmly 3 references support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins at 75% confidence or better
2030-09-30 is the interconnection record’s requested in-service date, not a verified opening or commercial-operation day.
J4152 is a 250 MW photovoltaic generation interconnection request in Redwood, MN. The grid operator lists its queue status as Active. The requested in-service date is 2030-09-30; this is a planning date.
White Pines Commerce Park, Caughdenoy Road, Clay, Onondaga County, New York 13041, United StatesMicron Technology
DELAYEDDate confidence: DELAYEDThe date has movedHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all DELAYED pins3 years late75% CONFIDENCEOverall confidence: 75%How well the pin's source and references back up its dates.Weighted average of how firmly 12 references, the source included, support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins at 75% confidence or better
CNY Signal[9] (17 Apr 2026, updated 5 May 2026) reports Fab 1 operations in late 2030, revised from 2028; late 2030 mapped to October 2030 at month precision. Later fabs follow into the 2040s.
Micron's up to $100 billion, four-fab Clay, New York campus is projected to use about 16 billion kWh (16 TWh) a year at full buildout, served by National Grid through an expanded Clay substation and eight underground 345 kV lines; first-fab operations are now expected in 2030.
ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins65% CONFIDENCEOverall confidence: 65%How well the pin's source and references back up its dates.Weighted average of how firmly 2 references, the source included, support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins from 50% to 74% confidence
Wikipedia's[1][2] article dates it "scheduled to take place in Ahmedabad, Gujarat, India, in October 2030". Only the month is fixed so far, so the pin covers the whole of it.
The 2030 Commonwealth Games, officially known as the XXIV Commonwealth Games and commonly known as Amdavad 2030, is a planned multi-sport event scheduled to take place in Ahmedabad, Gujarat, India, in October 2030. This will be the second Commonwealth Games to be hosted in India, following the 2010 Games in Delhi, and the third in Asia. The article's infobox names Narendra Modi Stadium as the main venue, and its venue table lists the Sardar Vallabhbhai Patel Sports Enclave around it as the ceremonies venue, capacity 132,000.
ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins71% CONFIDENCEOverall confidence: 71%How well the pin's source and references back up its dates.Weighted average of how firmly 4 references, the source included, support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins from 50% to 74% confidence
Given as a target, not a fixed date, per the pin description: "…n a purpose-built site north of Riyadh. Estimated date.…"
Saudi Arabia hosts the World Expo for the first time, on a purpose-built site north of Riyadh. Estimated date.
Near Wakefield, Sussex County, Virginia, United States (town centroid used; project spans multiple parcels)Clenera
ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins70% CONFIDENCEOverall confidence: 70%How well the pin's source and references back up its dates.Weighted average of how firmly 6 references, the source included, support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins from 50% to 74% confidence
No developer date is published. Cleanview[4] lists expected commercial operation October 2030 and InfraSure's PJM-queue summary gives a proposed in-service date of 2030-10-01 (it also contains a conflicting October 2029 line).
Idaho-based Clenera's Blackwater Solar in Sussex County, Virginia is described as 500 MW (WHRO, approved 4,200-acre plan), 600 MWac (Clenera FAQ, WAVY) and 800 MW (PJM queue AE1-173 via trackers); WAVY reported a cost of nearly 1.1 billion USD for the 600 MW version, and the Board of Supervisors approved a revised project in 2025 after rejecting the first in 2024.
Washington Clean Energy Storage Complex, US Highway 75 & State Highway 133 Corridor, Blair, Washington County, NE 68008
ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins95% CONFIDENCEOverall confidence: 95%How well the pin's source and references back up its dates.Weighted average of how firmly 3 references support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins at 75% confidence or better
2030-10-01 is the interconnection record’s requested in-service date, not a verified opening or commercial-operation day.
GEN-2018-025 is a 200 MW battery storage interconnection request in Washington, NE. The grid operator lists its queue status as IA FULLY EXECUTED/ON SCHEDULE. The requested in-service date is 2030-10-01; this is a planning date.
Estimated: TeraWulf Muskie Campus Building 6, US Route 23 Industrial Corridor, Catlettsburg, Boyd County, KY 41129TeraWulf
UNVERIFIEDDate confidence: UNVERIFIEDNo wording about the date was foundHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all UNVERIFIED pins72% CONFIDENCEOverall confidence: 72%How well the pin's source and references back up its dates.Weighted average of how firmly 3 references support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins from 50% to 74% confidence
Separate construction cost, IT power, floor area and an opening date for this building or phase have not been verified. Published campus figures do not establish independent component figures.
SCHEDULEDDate confidence: SCHEDULEDGiven as scheduledHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all SCHEDULED pins82% CONFIDENCEOverall confidence: 82%How well the pin's source and references back up its dates.Weighted average of how firmly 3 references, the source included, support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins at 75% confidence or better
NASA's[1][2][3] eclipse catalogue gives the instant of greatest eclipse as 06:50:19 UT on 2030-11-25 (06:51:37 TD, the two separated by delta-T), from Saros series 133. Eclipse circumstances are computed from orbital mechanics, so the date and time are exact centuries ahead.
The Moon's shadow touches down at 06:50:19 UT on 2030-11-25, and the total phase lasts up to 3 minutes 44 seconds along a path 169.3 km wide crossing Botswana, S. Africa and Australia. A partial eclipse is visible from southern Africa, southern Indian Oc., the East Indies, Australia and Antarctica.
Grant Clean Solar Farm, US Route 160 Corridor, Ulysses, Grant County, KS 67880
ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins95% CONFIDENCEOverall confidence: 95%How well the pin's source and references back up its dates.Weighted average of how firmly 3 references support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins at 75% confidence or better
2030-11-30 is the interconnection record’s requested in-service date, not a verified opening or commercial-operation day.
GEN-2021-023 is a 306.18 MW photovoltaic generation interconnection request in Grant, KS. The grid operator lists its queue status as IA FULLY EXECUTED/ON SCHEDULE. The requested in-service date is 2030-11-30; this is a planning date.
SCHEDULEDDate confidence: SCHEDULEDGiven as scheduledHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all SCHEDULED pins79% CONFIDENCEOverall confidence: 79%How well the pin's source and references back up its dates.Weighted average of how firmly 3 references, the source included, support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins at 75% confidence or better
Given as scheduled, per en.wikipedia.org[1]: "…Riga) to the Lithuania-Poland border is scheduled for 2030, with completion of the double track rail…"
A European-gauge high-speed line finally connecting Estonia, Latvia and Lithuania to the rest of the EU rail network. Estimated date.
North of London, Madison County, Ohio (Somerford Township point used for coordinates)Savion
ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins72% CONFIDENCEOverall confidence: 72%How well the pin's source and references back up its dates.Weighted average of how firmly 5 references, the source included, support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins from 50% to 74% confidence
Cleanview[2] lists expected operation December 2030; Canary Media[1] (21 Sep 2026) and Agri-Pulse[5] say construction can begin next year (2027). No operation date has been published by Savion.
Savion's Oak Run Solar in Madison County, Ohio, an 800 MW solar and 300 MW battery agrivoltaic project estimated at $1 billion, won its Ohio Power Siting Board permit again on 17 September 2026 after the Ohio Supreme Court remanded one visual-impact issue; construction is expected to start in 2027.
ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins63% CONFIDENCEOverall confidence: 63%How well the pin's source and references back up its dates.Weighted average of how firmly 3 references, the source included, support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins from 50% to 74% confidence
Given as a target, not a fixed date, per the pin description: "…120 million passengers a year by 2030. Estimated date.…"
Six runways and 57 square kilometres of terminal city, designed to handle 120 million passengers a year by 2030. Estimated date.
ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins95% CONFIDENCEOverall confidence: 95%How well the pin's source and references back up its dates.Weighted average of how firmly 1 reference supports the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins at 75% confidence or better
NYISO[1] C26-0020 proposed COD column 12-2030; month precision. Initial backfeed 10-2030 and sync 11-2030 are distinct.
NYISO’s current workbook lists Brookside Forest C26-0020, customer Brookside Forest Energy Storage LLC, as a 300 MW / 1,200 MWh four-hour proposal at the 115 kV Waters Road Station. Proposed COD is December 2030, replacing the invented end-2028 schedule and $280M budget.