OpenAI's Stargate campus in Abilene, Texas, is Crusoe's eight-building, roughly 4 million sq ft, 1.2 GW development leased to Oracle. Construction began in 2024; Oracle reported six of eight buildings delivered on September 10, 2026, with the last two still being fitted out. A $15 billion joint venture funds the campus. Epoch AI estimates 618 MW of IT power now and 824 MW when complete.
Vantage Data Centers' Lighthouse campus in Port Washington, Wisconsin, is the Stargate site for Oracle and OpenAI: four data center buildings on 672 acres with about 902 MW of critical IT load. The Common Council approved the development agreement in August 2025, groundbreaking followed in December 2025 and satellite imagery shows Buildings 1 and 2 roughly halfway roofed by July 2026. Vantage targets a 2028 opening, but a grid interconnection that needs a new Wisconsin PSC approval may push full load into mid-2028 or later.