Oliver County Board Tables Base Electron Power Plant Rezoning
已确认日期确定性: 已确认已公布为确定日期来源对日期的表述有多确定:已确认、已排期、预估、已推迟或未核实。显示所有“已确认”的图钉可信度 84%总体可信度: 84%该图钉的来源和参考资料对其日期的支持程度。包括来源在内的 5 份资料对图钉开始和结束时间支持程度的加权平均;资料每比最新的一份旧 180 天,权重减半显示所有可信度不低于 75% 的图钉Stated as done, per WDEA's 28 Aug 2026 newsletter: "The Oliver County Planning and Zoning Board tabled decisions Thursday on a proposed 1,200-megawatt power plant west of Center"; the county's agenda sets the Base Electron rezoning hearing for 7:10 PM on 27 August 2026.[1]
Oliver County's planning and zoning board held its first hearings on Base Electron's 1,200 MW gas-fired Missouri Bend Energy Center, the plant Babcock & Wilcox is to build for Applied Digital near Center, North Dakota, and tabled all four applications for more information and landowner outreach.