原标题: LAX's SkyLink Reaches Its December 8 Deadline to Carry Passengers
第一项始终是图钉的来源。总体可信度是各份资料对上方所用开始和结束时间支持程度的加权平均;资料每比最新的一份旧 180 天,权重减半。
The Bond Buyer(2026 年 9 月 21 日):债券持有人将贷款方最终期限推迟到 12 月,最理想的情况是“在 12 月 8 日前达成公用事业协议,并于当天开始向公众提供服务”;维基百科写明“项目最终期限为 2026 年 12 月 8 日”。
Construction was due in March 2023; systems demonstration testing began April 21, 2026; LINXS sued the city on July 9, 2026; Fitch downgraded the ~$1.2 billion LINXS bonds on July 21, 2026 citing the lenders' longstop of Oct. 8 and the project longstop of Dec. 8, 2026; on September 20, 2026 the lender longstop was aligned with the Dec. 8 project longstop.[1]
Reported the $3.34 billion project targeting passenger service in October 2026, after missing the World Cup, with officials aiming for Super Bowl LXI and the 2028 Olympics.[1]
KTLA 5: the developer of the LAX Automated People Mover is suing the city of Los Angeles over disputes tied to the delayed system.[1]